2312 N ELMGROVE ST 90031

Certificate Information: 2312 N ELMGROVE ST 90031

Application / Permit
24014-10000-00605
Plan Check / Job No.
B24LA02618
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of existing detached garage and storage with addition to an Accessory Dwelling Unit per ordinance
Permit Issued
Issued on 8/20/2024
Issuing Office
Metro
Current Status
CofO Issued on 12/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 LAWRENCE QUIRANTE
Corrections Issued 2/19/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 2/23/2024 APPLICANT
Applicant returned to address corrections 7/12/2024 ADAM HEGAZI
Plan Check Approved 7/26/2024 MINA HABILI
Issued 8/20/2024 APPLICANT
CofO in Progress 12/9/2025 HAMIK HARTOUNIAN
No Progress 12/11/2025 DEROLD HAUFF
CofO in Progress 12/11/2025 DEROLD HAUFF
Permit Finaled 12/13/2025 DEROLD HAUFF
CofO Issued 12/13/2025 DEROLD HAUFF
Permit Finaled 12/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/26/2024 DAVID LOPEZ
Sewer availability Cleared 3/28/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 4/1/2024 DAVID LOPEZ
Supp. Use District POD/CDO/TDO Cleared 7/9/2024 ASHLEY RODARTE
Construction near power lines Cleared 7/24/2024 RIDWAN HARDY

Contact Information

Contractor Nelson General Building Contractor; Lic. No.: 649194-B 4227 S WESTERN AVE      LOS ANGELES, CA 90062
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/31/2025 Conditional Approval JEFFREY MEAD
PLUMBING-Rough 2/4/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 2/11/2025 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 2/24/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/9/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 5/9/2025 Corrections Issued FREDDIE RIVERA
Green Building Rough 5/9/2025 Partial Inspection FREDDIE RIVERA
HVAC-Rough 5/9/2025 Corrections Issued FREDDIE RIVERA
MERV13>=Rough 5/9/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 5/9/2025 Approved FREDDIE RIVERA
ELECTRICAL-Rough 5/13/2025 Approved WILLIAM SIERRA
HVAC-Rough 5/13/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 5/14/2025 Corrections Issued OSVALDO PARAMO
Green Building Rough 5/14/2025 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/14/2025 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 5/15/2025 Conditional Approval ALEX COLIN
BUILDING-Rough-Frame 5/16/2025 Approved WILLIAM SIERRA
HVAC-Rough 5/16/2025 Approved WILLIAM SIERRA
Insulation 5/16/2025 Approved WILLIAM SIERRA
Drywall Nailing 5/21/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/21/2025 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 8/1/2025 Corrections Issued HAMIK HARTOUNIAN
Final 8/1/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 8/1/2025 Approved HAMIK HARTOUNIAN
HVAC-Final 8/1/2025 Approved HAMIK HARTOUNIAN
MERV13>=Final 8/1/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Final 8/1/2025 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 8/1/2025 Approved HAMIK HARTOUNIAN
Final 11/6/2025 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Approved HAMIK HARTOUNIAN
Final 11/13/2025 Corrections Issued HAMIK HARTOUNIAN
Service/Power Release 11/13/2025 Approved HAMIK HARTOUNIAN
Final 12/1/2025 Partial Inspection HAMIK HARTOUNIAN
Final 12/9/2025 OK to Issue CofO HAMIK HARTOUNIAN
Service/Power Release 12/9/2025 Approved HAMIK HARTOUNIAN