2312 N ELMGROVE ST 90031
Certificate Information: 2312 N ELMGROVE ST 90031
- Application / Permit
- 24014-10000-00605
- Plan Check / Job No.
- B24LA02618
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of existing detached garage and storage with addition to an Accessory Dwelling Unit per ordinance
- Permit Issued
- Issued on 8/20/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 2/19/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 2/23/2024 | APPLICANT |
| Applicant returned to address corrections | 7/12/2024 | ADAM HEGAZI |
| Plan Check Approved | 7/26/2024 | MINA HABILI |
| Issued | 8/20/2024 | APPLICANT |
| CofO in Progress | 12/9/2025 | HAMIK HARTOUNIAN |
| No Progress | 12/11/2025 | DEROLD HAUFF |
| CofO in Progress | 12/11/2025 | DEROLD HAUFF |
| Permit Finaled | 12/13/2025 | DEROLD HAUFF |
| CofO Issued | 12/13/2025 | DEROLD HAUFF |
| Permit Finaled | 12/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/28/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2024 | DAVID LOPEZ |
| Supp. Use District POD/CDO/TDO | Cleared | 7/9/2024 | ASHLEY RODARTE |
| Construction near power lines | Cleared | 7/24/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Nelson General Building Contractor; Lic. No.: 649194-B | 4227 S WESTERN AVE LOS ANGELES, CA 90062 |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/31/2025 | Conditional Approval | JEFFREY MEAD |
| PLUMBING-Rough | 2/4/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 2/11/2025 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/24/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/9/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/9/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 5/9/2025 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 5/9/2025 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Rough | 5/9/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/9/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/13/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 5/13/2025 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 5/14/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 5/14/2025 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/14/2025 | Partial Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 5/15/2025 | Conditional Approval | ALEX COLIN |
| BUILDING-Rough-Frame | 5/16/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 5/16/2025 | Approved | WILLIAM SIERRA |
| Insulation | 5/16/2025 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 5/21/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/21/2025 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 8/1/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 8/1/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 8/1/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 8/1/2025 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 8/1/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 8/1/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/1/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 11/6/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 11/13/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 11/13/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 12/1/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 12/9/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 12/9/2025 | Approved | HAMIK HARTOUNIAN |