2334 N GLOVER PL 90031

Certificate Information: 2334 N GLOVER PL 90031

Application / Permit
24014-10000-00590
Plan Check / Job No.
B24LA02532
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING 1 STORY SFD 1 OF 2
Permit Issued
Issued on 5/10/2024
Issuing Office
Metro
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 ARSALAN SHABESTARI
Corrections Issued 2/28/2024 ARSALAN SHABESTARI
Quality Review Completed 3/8/2024 KEN GILL
Building Plans Picked Up 3/8/2024 APPLICANT
Applicant returned to address corrections 4/5/2024 ARSALAN SHABESTARI
Plan Check Approved 5/9/2024 ARSALAN SHABESTARI
Issued 5/10/2024 APPLICANT
CofO in Progress 7/21/2025 HAMIK HARTOUNIAN
Permit Finaled 7/22/2025 DEROLD HAUFF
CofO Issued 7/22/2025 DEROLD HAUFF
Permit Finaled 7/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 4/12/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/17/2024 TREVOR QUAN
Low Impact Development (LID) Cleared 4/23/2024 ROGELIO CORTES
ZI Cleared 4/25/2024 FIPE LEILUA
Roof/Waste drainage to street Cleared 5/7/2024 TREVOR QUAN

Contact Information

Contractor Rodriguez Development Company; Lic. No.: 1106975-B 243 POINTE DRIVE      BREA, CA 92821

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/20/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/20/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/22/2024 Partial Approval JEFFREY MEAD
Underground Mechanical 5/22/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 5/29/2024 Partial Approval RICHARD DOCKUS
Insulation 5/31/2024 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/10/2024 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/10/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 7/10/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/29/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 8/29/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 8/29/2024 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/5/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/5/2024 Approved HAMIK HARTOUNIAN
Insulation 9/10/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 10/1/2024 Not Ready for Inspection THOMAS LOGRASSO
Pre-Inspection 1/30/2025 Partial Inspection WILLIAM SIERRA
Final 3/10/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 3/10/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/10/2025 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 3/10/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Not Ready HAMIK HARTOUNIAN
Final 4/9/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 4/9/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Approved HAMIK HARTOUNIAN
Final 7/1/2025 No Access for Inspection HAMIK HARTOUNIAN
Green Building Final 7/1/2025 No Access for Inspection HAMIK HARTOUNIAN
Final 7/15/2025 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 7/15/2025 Approved HAMIK HARTOUNIAN