1405 W KELLAM AVE 90026

Certificate Information: 1405 W KELLAM AVE 90026

Application / Permit
24014-10000-00561
Plan Check / Job No.
B24LA02422
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. 1. REHABILITATION & RENOVATION OF (E)3-STORY + BASEMENT SINGLE FAMILY RESIDENCE 2. STRUCTURAL REPAIR AND RECONSTRUCTION OF EXISTING BASEMENT RETAINING WALLS & FOUNDATION 3. NEW COVERED BASEMENT PORCH + EXTERIOR STAIRS AT REAR YARD 4. NEW ADDITION TO EXISTING FIRST FLOOR KITCHEN AT REAR YARD W/ OPEN ROOF DECK ABOVE 5. NEW COVERED REAR PORCH AT REAR YARD 6. NEW RESIDENTIAL HYDRAULIC ELEVATOR
Permit Issued
Issued on 2/26/2025
Issuing Office
Current Status
Issued on 2/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 ARSALAN SHABESTARI
Corrections Issued 2/17/2024 ARSALAN SHABESTARI
Quality Review Completed 3/5/2024 YOUNG KIM
Applicant returned to address corrections 7/24/2024 ARSALAN SHABESTARI
Applicant returned to address corrections 8/12/2024 ARSALAN SHABESTARI
Plan Check Approved 2/26/2025 ARSALAN SHABESTARI
Issued 2/26/2025 APPLICANT

Permit Application Clearance Information

CPC Cleared 3/7/2024 MAYELA VILLA
Sewer availability Cleared 3/13/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 4/15/2024 DAVID LOPEZ
City Hist. Cultural Monument Cleared 6/3/2024 LAMBERT GIESSINGER
HPOZ Cleared 6/3/2024 LAMBERT GIESSINGER
Historic monument Cleared 6/3/2024 LAMBERT GIESSINGER
Excavation more than 5-ft deep Cleared 2/14/2025 CALOSHA APPROVED
GPI Written Notices Cleared 2/24/2025 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 2/24/2025 ARSALAN SHABESTARI

Contact Information

Architect Guerrero,, Matthew David; Lic. No.: NA40191       ,
Contractor Owner-Builder       ,
Engineer Galbreath,, Sean; Lic. No.: NA5653       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2025 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/14/2025 Not Ready for Inspection WILLIAM SIERRA
METHANE-Barrier 4/14/2025 Not Ready for Inspection WILLIAM SIERRA
METHANE-Subgrade 4/14/2025 Not Ready for Inspection WILLIAM SIERRA
PLUMBING-Rough 4/16/2025 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 4/17/2025 Partial Approval HAMIK HARTOUNIAN
METHANE-Barrier 4/17/2025 Approved HAMIK HARTOUNIAN
METHANE-Subgrade 4/17/2025 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 4/21/2025 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 4/28/2025 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 5/7/2025 Partial Approval NICHOLAS LOPEZ
Deputy Reinf. Concrete 5/8/2025 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/14/2025 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/30/2025 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 6/26/2025 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 6/30/2025 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 8/19/2025 Partial Approval FREDDIE RIVERA