8102-8104 S CHASE AVE 90045
Certificate Information: 8102-8104 S CHASE AVE 90045
- Application / Permit
- 24014-10000-00550
- Plan Check / Job No.
- B24LA02380
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan existing garage to be converted to ADU with new addition per LAMC 12.22A.33(c) and (e). New SB9 unit on second floor per Two Unit Development CA Govt 65852.21. To be fully sprinklered NFPA 13D
- Permit Issued
- Issued on 2/3/2025
- Issuing Office
- Current Status
- Issued on 2/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 2/29/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 3/5/2024 | TU HUA |
| Applicant returned to address corrections | 7/9/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 8/14/2024 | MARCELA FRANQUEZ |
| Issued | 2/3/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2024 | DARIN LAM |
| Sewer availability | Cleared | 3/20/2024 | DARIN LAM |
| Hydrant and Access approval | Cleared | 4/12/2024 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 5/1/2024 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 5/4/2024 | BRENDEN HAWK |
| Specific Plan | Cleared | 5/8/2024 | EILEEN HUNT |
| Construction near power lines | Cleared | 6/26/2024 | EDGAR PASCUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2026 | Partial Inspection | JESUS PINEDA |
| Special/Order Compliance | 2/10/2026 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 3/10/2026 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 3/13/2026 | Partial Approval | JESUS PINEDA |
| Special/Order Compliance | 3/13/2026 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 3/19/2026 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 3/23/2026 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 4/27/2026 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 5/19/2026 | Approved | MICHAEL LEWIS |
| Sewer | 6/4/2026 | Approved | ANTHONY EGSON |