4515 E RUSSELL AVE 90027
Certificate Information: 4515 E RUSSELL AVE 90027
- Application / Permit
- 24014-10000-00528
- Plan Check / Job No.
- B24LA02247
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL. CONVERT (E) DUPLEX TO SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 9/4/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | CARLOS MONTES |
| Corrections Issued | 2/27/2024 | CARLOS MONTES |
| Quality Review Completed | 3/4/2024 | KEN GILL |
| Applicant returned to address corrections | 6/14/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 7/10/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 7/18/2024 | CARLOS MONTES |
| Plan Check Approved | 8/29/2024 | CARLOS MONTES |
| Issued | 9/4/2024 | APPLICANT |
| No Progress | 1/10/2026 | DEROLD HAUFF |
| CofO in Progress | 1/10/2026 | DEROLD HAUFF |
| No Progress | 1/13/2026 | RAUL BARAJAS |
| CofO in Progress | 1/13/2026 | RAUL BARAJAS |
| CofO in Progress | 1/14/2026 | ENRIQUE MIRELES |
| No Progress | 1/14/2026 | DEROLD HAUFF |
| CofO in Progress | 1/14/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
| CofO Issued | 1/21/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/4/2024 | DAVID LOPEZ |
| Specific Plan | Cleared | 4/9/2024 | YAMILLET BRIZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | DAVID LOPEZ |
| Tenant Habitability Plan | Cleared | 6/3/2024 | RICARDO BOHORQUEZ |
| Low Impact Development (LID) | Cleared | 6/7/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/10/2024 | DAVID LOPEZ |
| Demo/Removal of Rental Units | Cleared | 7/31/2024 | SUSAN LIM |
| GPI Written Notices | Cleared | 8/7/2024 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 8/7/2024 | CARLOS MONTES |
Contact Information
| Contractor | F H S Construction Inc; Lic. No.: 1027487-B | 1025 N BRIGHTON ST BURBANK, CA 91506 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/11/2024 | Approved | ENRIQUE MIRELES |
| Deputy Steel/Welding | 10/28/2024 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/29/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 10/31/2024 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/2/2025 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/2/2025 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/7/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/7/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 4/1/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/11/2025 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/11/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/15/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 4/15/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/18/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/22/2025 | Approved | ENRIQUE MIRELES |
| Insulation | 4/25/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 5/22/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 5/27/2025 | Approved | ENRIQUE MIRELES |
| Final | 10/6/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/6/2025 | Approved | ENRIQUE MIRELES |
| Green Building Final | 10/6/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/6/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/6/2025 | Approved | ENRIQUE MIRELES |
| Final | 10/14/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 10/17/2025 | Conditional Approval | ENRIQUE MIRELES |
| Final | 12/26/2025 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 12/30/2025 | Corrections Issued | ENRIQUE MIRELES |
| Final | 1/7/2026 | OK to Issue CofO | ENRIQUE MIRELES |