9508-9508 1/2 S GRAPE ST 90002

Certificate Information: 9508-9508 1/2 S GRAPE ST 90002

Application / Permit
24014-10000-00508
Plan Check / Job No.
B24LA02118
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED 2-CAR GARAGE WITHIN (E) 1-STORY SFD TO ADU AND SECOND STORY ADU ADDITION PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 9/10/2025
Issuing Office
Metro
Current Status
Issued on 9/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/6/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 VIVIAN LAO
Corrections Issued 2/29/2024 VIVIAN LAO
Quality Review Completed 3/6/2024 KEN GILL
Building Plans Picked Up 3/28/2024 APPLICANT
Applicant returned to address corrections 6/11/2025 VIVIAN LAO
Applicant returned to address corrections 7/17/2025 VIVIAN LAO
Plan Check Approved 8/26/2025 VIVIAN LAO
Issued 9/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/1/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 4/1/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 7/30/2025 ADRIAN SANCHEZ
Sewer availability Cleared 7/30/2025 ADRIAN SANCHEZ

Contact Information

Contractor Stampede General Construction; Lic. No.: 1101224-B 1344 W 54TH STREET      LOS ANGELES, CA 90037
Engineer Vo,, Tung Thanh; Lic. No.: C69546 11122 BIXLER CIRCLE      GARDEN GROVE, CA 92840

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/14/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 10/14/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 10/14/2025 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 10/27/2025 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 10/29/2025 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 12/16/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 12/16/2025 Not Ready for Inspection ARTHUR NEGRETE
Wood Frame 12/16/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 2/4/2026 Not Ready for Inspection JOSEPH MCGARRY
Gas Test 2/4/2026 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 2/4/2026 Not Ready for Inspection JOSEPH MCGARRY
Sewer 2/4/2026 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 2/12/2026 Approved JOSEPH MCGARRY
Gas Test 2/12/2026 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 2/12/2026 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 2/12/2026 Approved JOSEPH MCGARRY
HVAC-Rough 4/1/2026 Approved ARTHUR NEGRETE
Insulation 4/1/2026 Approved ARTHUR NEGRETE
Drywall Nailing 4/6/2026 Approved ARTHUR NEGRETE
Green Building Rough 4/6/2026 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 4/6/2026 Approved ARTHUR NEGRETE
Shower Pan 4/28/2026 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 4/29/2026 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 6/18/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 6/18/2026 Approved ARTHUR NEGRETE
Final 6/18/2026 Not Ready for Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 6/18/2026 Approved ARTHUR NEGRETE
Gas Test 6/18/2026 Approved ARTHUR NEGRETE
Green Building Final 6/18/2026 Corrections Issued ARTHUR NEGRETE
HVAC-Final 6/18/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 6/18/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 6/18/2026 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 6/18/2026 Approved ARTHUR NEGRETE
Final 7/23/2026 No Result Entered ARTHUR NEGRETE
Green Building Final 7/23/2026 No Result Entered ARTHUR NEGRETE