1312 W 80TH ST 90044

Certificate Information: 1312 W 80TH ST 90044

Application / Permit
24014-10000-00505
Plan Check / Job No.
B24LA02094
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Ground Floor Addition to (E) 1-Story SFD
Permit Issued
Issued on 11/9/2024
Issuing Office
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2024 APPLICANT
Assigned to Plan Check Engineer 2/9/2024 DAVID CASTILLO
Corrections Issued 2/12/2024 DAVID CASTILLO
Applicant returned to address corrections 2/15/2024 EDWIN ESPIN
Applicant returned to address corrections 3/14/2024 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/7/2024 EDWIN ESPIN
Applicant returned to address corrections 7/19/2024 DAVID CASTILLO
Plan Check Approved 11/8/2024 DAVID CASTILLO
Issued 11/9/2024 APPLICANT
CofO in Progress 3/4/2025 JOHN QUINTANILLA
Permit Finaled 3/6/2025 DEROLD HAUFF
CofO Issued 3/6/2025 DEROLD HAUFF
Permit Finaled 3/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/13/2024 ARNULFO CHAMU
Sewer availability Cleared 2/13/2024 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 2/14/2024 ARNULFO CHAMU
Community Plan Implem. Overlay Cleared 9/24/2024 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/22/2024 Conditional Approval MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 11/26/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 11/26/2024 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 12/2/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 12/2/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Partial Approval MICHAEL LEWIS
Insulation 12/10/2024 Not Ready for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Partial Approval MICHAEL LEWIS
Insulation 12/12/2024 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 12/16/2024 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 12/16/2024 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 12/26/2024 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Approved JOHN QUINTANILLA
HVAC-Rough 12/26/2024 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 12/26/2024 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Rough 1/3/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 1/3/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 1/13/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 1/13/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 1/13/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 1/15/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 1/15/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 1/21/2025 Approved JOHN QUINTANILLA
Green Building Rough 1/21/2025 Approved JOHN QUINTANILLA
Insulation 1/21/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 1/21/2025 Approved JOHN QUINTANILLA
Drywall Nailing 1/28/2025 Approved JOHN QUINTANILLA
Final 2/24/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 2/24/2025 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/24/2025 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 2/24/2025 Approved JOHN QUINTANILLA
Green Building Final 2/26/2025 Approved JOHN QUINTANILLA
Final 3/3/2025 OK to Issue CofO JOHN QUINTANILLA