8901 S DALTON AVE 90047

Certificate Information: 8901 S DALTON AVE 90047

Application / Permit
24014-10000-00503
Plan Check / Job No.
B24LA02086
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Addition to single family structure
Permit Issued
Issued on 2/16/2024
Issuing Office
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2024 APPLICANT
Assigned to Plan Check Engineer 2/6/2024 ZAW HAN
Corrections Issued 2/6/2024 ZAW HAN
Plan Check Approved 2/15/2024 ZAW HAN
Issued 2/16/2024 APPLICANT
CofO in Progress 8/8/2024 JOSE MACIAS
CofO Issued 9/3/2024 RUBEN SALAS
Permit Finaled 9/3/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/12/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 2/12/2024 JEANIE LAM
Sewer availability Cleared 2/12/2024 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/14/2024 No Access for Inspection JOSE MACIAS
Footing/Foundation/Slab 3/19/2024 Approved JOSE MACIAS
Insulation 3/29/2024 Partial Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 4/2/2024 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/10/2024 Not Ready for Inspection JOSE MACIAS
Green Building Rough 4/10/2024 Not Ready for Inspection JOSE MACIAS
ELECTRICAL-Rough 4/16/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 4/16/2024 Approved JOSE MACIAS
HVAC-Rough 4/16/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Approved JOSE MACIAS
PLUMBING-Rough 4/23/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 4/30/2024 Approved JOSE MACIAS
Insulation 5/2/2024 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 5/6/2024 Approved JOSE MACIAS
Green Building Rough 5/6/2024 Approved JOSE MACIAS
Insulation 5/6/2024 Approved JOSE MACIAS
Drywall Nailing 5/9/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 5/13/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 5/15/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Not Ready JOSE MACIAS
Final 7/18/2024 Corrections Issued JOSE MACIAS
Green Building Final 7/18/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Not Ready JOSE MACIAS
Smoke Detectors 7/18/2024 Approved JOSE MACIAS
Final 7/22/2024 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Approved JOSE MACIAS
Final 8/7/2024 OK to Issue CofO JOSE MACIAS