12111 W ALLIN ST 90230
Certificate Information: 12111 W ALLIN ST 90230
- Application / Permit
- 24014-10000-00485
- Plan Check / Job No.
- B23LA24839
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/6/2025
- Issuing Office
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 2/9/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 10/7/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 11/20/2024 | MADISON ODELL |
| Plan Check Approved | 1/1/2025 | SARKIS HARABEDIAN |
| Issued | 1/6/2025 | APPLICANT |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
| CofO Issued | 6/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/29/2024 | FREDDY GARCIA |
| Address approval | Cleared | 7/25/2024 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 7/25/2024 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2024 | KIMBERLY HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/27/2025 | Partial Inspection | JESUS PINEDA |
| Sewer | 3/6/2025 | Corrections Issued | JESUS PINEDA |
| Underground Mechanical | 3/10/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 3/14/2025 | Approved | MICHAEL ALLEN |
| Deputy Drilled-In Anchors | 3/24/2025 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/26/2025 | Corrections Issued | RUBEN RIVAS |
| Special/Order Compliance | 3/26/2025 | Partial Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 3/28/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 4/1/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Approved | BOBBY KEY |
| Insulation | 4/2/2025 | Corrections Issued | BOBBY KEY |
| Insulation | 4/3/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 4/4/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Drywall Nailing | 4/7/2025 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 4/7/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/8/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 4/14/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 4/14/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 4/17/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 4/17/2025 | Approved | JAYLIN GRAVITTE |
| HVAC-Rough | 5/5/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 5/19/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 5/19/2025 | Approved | MICHAEL ALLEN |
| Final | 5/19/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 5/19/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 5/19/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 5/19/2025 | Approved | MICHAEL ALLEN |
| Final | 5/21/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 5/23/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Final | 5/29/2025 | Approved | RUBEN RIVAS |
| Final | 6/2/2025 | Conditional Approval | MICHAEL ALLEN |