131 N SERRANO AVE 90004

Certificate Information: 131 N SERRANO AVE 90004

Application / Permit
24014-10000-00474
Plan Check / Job No.
B24LA01993
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Convert (E) 443 square foot garage and add 354.5 square foot to Accessory dwelling unit (797.5sqft) per state law "COMPLY WITH DEPARTMENT ORDER effective date 01/02/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/12/2024
Issuing Office
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2024 APPLICANT
Assigned to Plan Check Engineer 2/5/2024 JOHN MESIAS
Corrections Issued 2/7/2024 JOHN MESIAS
Applicant returned to address corrections 5/7/2024 KHUONG TRUONG
Applicant returned to address corrections 5/10/2024 KHUONG TRUONG
Plan Check Approved 6/13/2024 KHUONG TRUONG
Issued 7/12/2024 APPLICANT
CofO in Progress 11/18/2025 WILLIAM MICHALAK
Permit Finaled 11/19/2025 DANIEL SANCHEZ
CofO Issued 11/19/2025 DANIEL SANCHEZ
Permit Finaled 11/19/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 2/10/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 2/10/2024 CELINA MORENO
Historic Resource Verification Cleared 2/13/2024 RAFAEL FONTES
Eng Process Fee Ord 176,300 Cleared 2/16/2024 CELINA MORENO
Sewer availability Cleared 2/16/2024 CELINA MORENO
Redevelopment Project Area Cleared 2/17/2024 YASMINE BASHIRI
Construction near power lines Cleared 6/7/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: NA93320       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/19/2024 Approved WILLIAM MICHALAK
Footing/Foundation/Slab 10/8/2024 Not Ready for Inspection WILLIAM MICHALAK
PLUMBING-Rough 10/8/2024 Corrections Issued WILLIAM MICHALAK
Deputy Drilled-In Anchors 10/18/2024 Approved WILLIAM MICHALAK
Footing/Foundation/Slab 10/25/2024 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 1/13/2025 Not Ready for Inspection WILLIAM MICHALAK
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval WILLIAM MICHALAK
Green Building Rough 1/13/2025 Corrections Issued WILLIAM MICHALAK
Rough-Elec/Plmb/HVAC 1/13/2025 Corrections Issued WILLIAM MICHALAK
Rough-Elec/Plmb/HVAC 1/27/2025 Not Ready for Inspection LUIS CORRAL
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Approved WILLIAM MICHALAK
Insulation 2/25/2025 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 2/25/2025 Partial Approval WILLIAM MICHALAK
Drywall Nailing 4/7/2025 Corrections Issued WILLIAM MICHALAK
Green Building Rough 4/7/2025 Corrections Issued WILLIAM MICHALAK
Interior/Exterior Lathing 4/28/2025 Partial Approval WILLIAM MICHALAK
Gas Test 6/2/2025 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 6/2/2025 Approved WILLIAM MICHALAK
Sewer 6/2/2025 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 7/9/2025 Approved WILLIAM MICHALAK
Drywall Nailing 7/9/2025 Approved WILLIAM MICHALAK
Final 7/9/2025 Corrections Issued WILLIAM MICHALAK
Green Building Final 7/9/2025 Approved WILLIAM MICHALAK
Green Building Rough 7/9/2025 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 7/9/2025 Approved WILLIAM MICHALAK
Final 8/12/2025 OK to Issue CofO WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/12/2025 SGSOV Approved WILLIAM MICHALAK