5829 N CLEON AVE 91601

Certificate Information: 5829 N CLEON AVE 91601

Application / Permit
24014-10000-00472
Plan Check / Job No.
B24LA01987
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ATTACHED RECREATION ROOM CONNECTED VIA BREEZEWAY AND ADDITION TO EXISTING SINGLE FAMILY DWELLING (1-STORY)
Permit Issued
Issued on 11/22/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 CARLOS MONTES
Corrections Issued 2/13/2024 CARLOS MONTES
Quality Review Completed 2/14/2024 KEN GILL
Building Plans Picked Up 2/16/2024 APPLICANT
Applicant returned to address corrections 6/10/2024 CARLOS MONTES
Applicant returned to address corrections 10/29/2024 CARLOS MONTES
Plan Check Approved 11/22/2024 CARLOS MONTES
Issued 11/22/2024 APPLICANT
CofO in Progress 4/18/2026 RAUL OLAGI
CofO Issued 4/30/2026 RUBEN SALAS
Permit Finaled 4/30/2026 RUBEN SALAS

Permit Application Clearance Information

CPC Cleared 3/5/2024 RUBEN VASQUEZ
Construction near power lines Cleared 3/5/2024 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 3/7/2024 CARLOS RAMIREZ
Sewer availability Cleared 3/7/2024 CARLOS RAMIREZ
Low Impact Development Cleared 5/9/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 5/9/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: NA56232       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/29/2025 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 1/29/2025 Corrections Issued MISAEL ESPARZA
Pre-Inspection 1/29/2025 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 2/3/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 2/26/2025 Partial Approval JOSE AVILA
Wood Frame 2/28/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Partial Approval JOSE AVILA
Green Building Rough 5/5/2025 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 5/27/2025 Approved JOSE AVILA
Drywall Nailing 5/30/2025 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 7/8/2025 Conditional Approval JUAN VALENZUELA
Wood Frame 7/11/2025 Partial Inspection JOSE AVILA
BUILDING-Rough-Frame 7/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 7/22/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 7/22/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Approved JOSE AVILA
Drywall Nailing 7/30/2025 Partial Approval JOSE AVILA
Interior/Exterior Lathing 7/30/2025 Partial Approval JOSE AVILA
Insulation 8/25/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 8/25/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 9/17/2025 Approved JOSE AVILA
Insulation 9/17/2025 Approved JOSE AVILA
Service/Power Release 10/9/2025 Approved JOSE AVILA
Drywall Nailing 10/16/2025 Approved JOSE AVILA
Drywall Nailing 11/3/2025 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 1/13/2026 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/13/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/13/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/13/2026 Conditional Approval ROBERTO PALACIOS-LOPEZ
Insulation 1/13/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/13/2026 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 1/16/2026 Approved DAVID ANDERSON
Final 3/9/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 3/9/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 3/9/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 3/27/2026 Approved GAREN HAYRAPETYAN
Final 3/27/2026 Corrections Issued GAREN HAYRAPETYAN
HVAC-Final 3/27/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 3/27/2026 Approved GAREN HAYRAPETYAN
Final 4/8/2026 OK to Issue CofO GAREN HAYRAPETYAN