5829 N CLEON AVE 91601
Certificate Information: 5829 N CLEON AVE 91601
- Application / Permit
- 24014-10000-00472
- Plan Check / Job No.
- B24LA01987
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ATTACHED RECREATION ROOM CONNECTED VIA BREEZEWAY AND ADDITION TO EXISTING SINGLE FAMILY DWELLING (1-STORY)
- Permit Issued
- Issued on 11/22/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | CARLOS MONTES |
| Corrections Issued | 2/13/2024 | CARLOS MONTES |
| Quality Review Completed | 2/14/2024 | KEN GILL |
| Building Plans Picked Up | 2/16/2024 | APPLICANT |
| Applicant returned to address corrections | 6/10/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 10/29/2024 | CARLOS MONTES |
| Plan Check Approved | 11/22/2024 | CARLOS MONTES |
| Issued | 11/22/2024 | APPLICANT |
| CofO in Progress | 4/18/2026 | RAUL OLAGI |
| CofO Issued | 4/30/2026 | RUBEN SALAS |
| Permit Finaled | 4/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| CPC | Cleared | 3/5/2024 | RUBEN VASQUEZ |
| Construction near power lines | Cleared | 3/5/2024 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 3/7/2024 | CARLOS RAMIREZ |
| Low Impact Development | Cleared | 5/9/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/9/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: NA56232 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/29/2025 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/29/2025 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 1/29/2025 | Partial Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/3/2025 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/26/2025 | Partial Approval | JOSE AVILA |
| Wood Frame | 2/28/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Partial Approval | JOSE AVILA |
| Green Building Rough | 5/5/2025 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 5/27/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 5/30/2025 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 7/8/2025 | Conditional Approval | JUAN VALENZUELA |
| Wood Frame | 7/11/2025 | Partial Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 7/22/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/22/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 7/22/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 7/30/2025 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 7/30/2025 | Partial Approval | JOSE AVILA |
| Insulation | 8/25/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 8/25/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 9/17/2025 | Approved | JOSE AVILA |
| Insulation | 9/17/2025 | Approved | JOSE AVILA |
| Service/Power Release | 10/9/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 10/16/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 11/3/2025 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 1/13/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 1/13/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 1/13/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 1/13/2026 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 1/13/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 1/13/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 1/16/2026 | Approved | DAVID ANDERSON |
| Final | 3/9/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 3/9/2026 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/9/2026 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 3/27/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 3/27/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Final | 3/27/2026 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Final | 3/27/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 4/8/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |