12018 W SARAH ST 91607

Certificate Information: 12018 W SARAH ST 91607

Application / Permit
24014-10000-00468
Plan Check / Job No.
B24LA01960
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New addition at rear of existing one story single family dwelling.
Permit Issued
Issued on 7/3/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2024 APPLICANT
Assigned to Plan Check Engineer 2/12/2024 AUNG SOE
Corrections Issued 2/14/2024 AUNG SOE
Building Plans Picked Up 2/15/2024 APPLICANT
Applicant returned to address corrections 3/20/2024 NEHEMIAS RAMOS
Plan Check Approved 6/28/2024 ADAM HEGAZI
Issued 7/3/2024 APPLICANT
CofO in Progress 4/18/2025 JAVIER RAMOS JR
CofO Issued 5/12/2025 RUBEN SALAS
Permit Finaled 5/12/2025 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 2/23/2024 YINGSHI HUANG
Eng Process Fee Ord 176,300 Cleared 3/2/2024 CARLOS AGUILERA
Sewer availability Cleared 3/2/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 4/10/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 4/11/2024 CARLOS AGUILERA
Construction near power lines Cleared 6/21/2024 RIDWAN HARDY
Construction within easement Cleared 6/21/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Aws, Salahaldin; Lic. No.: C95446 100 DESERT LOTUS      IRVINE, CA 92618

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/15/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 7/15/2024 Corrections Issued CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 7/22/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 7/24/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 7/24/2024 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 7/24/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/6/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 8/6/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 8/21/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 8/21/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 9/19/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 9/19/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 9/20/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Gas Test 10/2/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 10/2/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 10/2/2024 Approved CHRISTOPHER ROJAS
Shower Pan 10/2/2024 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 10/2/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/7/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 10/10/2024 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 10/10/2024 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 10/10/2024 Not Ready for Inspection GAREN HAYRAPETYAN
MERV13>=Rough 10/10/2024 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 10/18/2024 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/18/2024 Partial Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Partial Inspection CHRISTOPHER ROJAS
Green Building Rough 10/18/2024 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/22/2024 Partial Approval DAVID ANDERSON
Wood Frame 10/22/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/4/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/5/2024 Partial Approval CHRISTOPHER ROJAS
Insulation 11/18/2024 Approved LOUIS ESCOTO
Drywall Nailing 11/25/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/27/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/5/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 3/11/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 3/11/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 3/11/2025 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 3/11/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 3/13/2025 Approved CHRISTOPHER ROJAS
Final 3/13/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 3/13/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Final 3/13/2025 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/25/2025 Approved JAVIER RAMOS JR
Final 3/25/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 3/25/2025 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 3/25/2025 Approved JAVIER RAMOS JR
HVAC-Final 3/25/2025 Approved JAVIER RAMOS JR
MERV13>=Final 3/25/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 3/25/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/25/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 3/25/2025 Approved JAVIER RAMOS JR
Smoke Detectors 3/25/2025 Approved JAVIER RAMOS JR
Final 4/17/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 4/17/2025 Approved JAVIER RAMOS JR