2112 W CAMORILLA DR 90065

Certificate Information: 2112 W CAMORILLA DR 90065

Application / Permit
24014-10000-00443
Plan Check / Job No.
B24LA01838
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: PATIO COVER ADDITION (200SF ) AND EXTERIOR ALTERATION TO INSTALL 2 WINDOWS AND 1 SLIDING DOORS TO (E) SFD. ALL WORK PER ENG.
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
CofO Issued on 6/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2024 APPLICANT
Assigned to Plan Check Engineer 2/5/2024 LUISANGEL VALENZUELA
Corrections Issued 2/6/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/14/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 9/21/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 10/2/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/27/2025 LUISANGEL VALENZUELA
Plan Check Approved 3/4/2025 LUISANGEL VALENZUELA
Issued 3/25/2025 APPLICANT
CofO in Progress 6/12/2025 NICHOLAS LOPEZ
Permit Finaled 6/14/2025 DEROLD HAUFF
CofO Issued 6/14/2025 DEROLD HAUFF
Permit Finaled 6/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/14/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 8/21/2024 JUSTIN BICOL
Construction near power lines Cleared 8/22/2024 JOSHUA MARTIN
Grading Pre-Inspection Cleared 8/30/2024 LANNY MERRICK
Specific Plan Cleared 2/26/2025 PABLO ESTRADA
ZI Cleared 2/26/2025 PABLO ESTRADA

Contact Information

Contractor Owner-Builder       ,
Engineer Desai,, Anil T; Lic. No.: C24653 1530 VIA LOS COYOTES      LA HABRA, CA 90631

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/2/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Partial Approval NICHOLAS LOPEZ
Green Building Rough 4/21/2025 Not Ready for Inspection NICHOLAS LOPEZ
ELECTRICAL-Rough 4/25/2025 Approved NICHOLAS LOPEZ
Insulation 4/25/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 4/25/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 4/29/2025 Approved NICHOLAS LOPEZ
Green Building Rough 4/29/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 5/22/2025 Approved NICHOLAS LOPEZ
Final 5/22/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 5/22/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 5/22/2025 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 5/22/2025 Approved NICHOLAS LOPEZ
Final 6/12/2025 OK to Issue CofO NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Approved NICHOLAS LOPEZ