101 N OCEAN AVE 90402
Certificate Information: 101 N OCEAN AVE 90402
- Application / Permit
- 24014-10000-00439
- Plan Check / Job No.
- B24LA01827
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (19) Marquee Sign
- Work Description
- PROPOSED POOL DECK EXTENSION TO (E) MULTIFAMILY. ADD NEW AREA DRAINS AND REPAIR ANY (E) DRAIN LINES.
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Current Status
- Issued on 4/10/2024
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | JOE VO |
| Corrections Issued | 2/4/2024 | JOE VO |
| Quality Review Completed | 2/5/2024 | PRANITA SHAH |
| Assigned to Zoning Architect | 2/8/2024 | JOE VO |
| Applicant returned to address corrections | 3/4/2024 | JOE VO |
| Plan Check Approved | 4/10/2024 | JOE VO |
| Issued | 4/10/2024 | APPLICANT |
Permit Application Clearance Information
| Coastal Zone | Cleared | 2/20/2024 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 2/20/2024 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 2/20/2024 | RUBEN VASQUEZ |
| ZA Case | Cleared | 2/20/2024 | RUBEN VASQUEZ |
| DAS Clearance | Cleared | 2/22/2024 | Cristina Salazar |
| Low Impact Development (LID) | Cleared | 3/28/2024 | TOMMY YIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 3/30/2024 | LIAM ODONOVAN |
| Zoning Plan Check | Cleared | 4/10/2024 | JOE VO |
Contact Information
| Architect | Hawkins,, Eric Shea; Lic. No.: NA36205 | , |
| Contractor | F N Construction Inc; Lic. No.: 905630-B | , |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/12/2024 | Approved | GRANT WOODS |
| Special/Order Compliance | 4/24/2024 | Not Ready for Inspection | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Partial Approval | RICARDO ROBLES |
| Masonry Wall/Backfill | 5/16/2024 | Corrections Issued | DERRICK SPENCER |
| Final | 10/28/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Final | 10/31/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Final | 11/4/2024 | Not Ready for Inspection | GRANT WOODS |
| Final | 11/8/2024 | Not Ready for Inspection | CASIMIR BRITTON |