8300 S WILEY POST AVE 90045

Certificate Information: 8300 S WILEY POST AVE 90045

Application / Permit
24014-10000-00431
Plan Check / Job No.
B24LA01810
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan. Addition and remodel to existing duplex COMPLY WITH DEPARTMENT ORDER effective date 07/11/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 1012607.
Permit Issued
Issued on 8/28/2024
Issuing Office
Current Status
CofO Issued on 5/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2024 APPLICANT
Assigned to Plan Check Engineer 2/5/2024 HUAN LE
Corrections Issued 2/13/2024 HUAN LE
Applicant returned to address corrections 2/21/2024 AMY GUEVARRA
Applicant returned to address corrections 5/31/2024 AMY GUEVARRA
Applicant returned to address corrections 7/10/2024 AMY GUEVARRA
Plan Check Approved 7/15/2024 AMY GUEVARRA
Issued 8/28/2024 APPLICANT
CofO in Progress 4/23/2025 ANDREW BEELI
Permit Finaled 5/7/2025 CLAUDIO MORENO
CofO Issued 5/7/2025 CLAUDIO MORENO
Permit Finaled 5/7/2025 CLAUDIO MORENO

Permit Application Clearance Information

Sewer availability Cleared 2/26/2024 BRENDEN HAWK
Specific Plan Cleared 3/21/2024 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 4/22/2024 BRENDEN HAWK
Low Impact Development (LID) Cleared 5/3/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/30/2024 BRENDEN HAWK

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/3/2024 Partial Approval ANDREW BEELI
Excavation/Setback/Form/Re-Bar 9/3/2024 Approved ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 Not Ready for Inspection ANDREW BEELI
PLUMBING-Rough 9/24/2024 Approved ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Approved ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Approved ANDREW BEELI
Deputy Wood Construction 10/15/2024 Partial Approval ANDREW BEELI
Deputy Wood Construction 10/24/2024 Partial Approval ANDREW BEELI
BUILDING-Rough-Frame 11/22/2024 Not Ready for Inspection ANDREW BEELI
Green Building Rough 11/22/2024 Not Ready for Inspection ANDREW BEELI
Rough-Elec/Plmb/HVAC 11/22/2024 Approved ANDREW BEELI
BUILDING-Rough-Frame 12/6/2024 Not Ready for Inspection ANDREW BEELI
Green Building Rough 12/6/2024 Not Ready for Inspection ANDREW BEELI
BUILDING-Rough-Frame 12/12/2024 Approved ANDREW BEELI
Green Building Rough 12/12/2024 Approved ANDREW BEELI
Insulation 12/17/2024 Approved ANDREW BEELI
Interior/Exterior Lathing 12/17/2024 Approved ANDREW BEELI
Drywall Nailing 12/26/2024 Approved ANDREW BEELI
Interior/Exterior Lathing 12/26/2024 Approved ANDREW BEELI
Final 2/25/2025 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 2/25/2025 Approved ANDREW BEELI
Green Building Final 2/25/2025 Approved ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 2/25/2025 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 2/25/2025 Approved ANDREW BEELI
Final 2/28/2025 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Approved ANDREW BEELI
Final 4/23/2025 OK to Issue CofO ANDREW BEELI