5249-5251 E ALDAMA ST 90042

Certificate Information: 5249-5251 E ALDAMA ST 90042

Application / Permit
24014-10000-00417
Plan Check / Job No.
B24LA01741
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ADDITION OF A 20'-5" X 19'-4" ADU TO AN (E) SFD W/ ATTACHED GARAGE PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENG.
Permit Issued
Issued on 3/18/2024
Issuing Office
Current Status
CofO Issued on 10/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2024 APPLICANT
Assigned to Plan Check Engineer 2/2/2024 LUISANGEL VALENZUELA
Corrections Issued 2/5/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/22/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/11/2024 LUISANGEL VALENZUELA
Plan Check Approved 3/14/2024 LUISANGEL VALENZUELA
Issued 3/18/2024 APPLICANT
CofO in Progress 9/5/2024 ROY SPAULDING
Permit Finaled 10/3/2024 RUBEN SALAS
CofO Issued 10/3/2024 RUBEN SALAS
Permit Finaled 10/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/6/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 2/6/2024 JUSTIN BICOL
Sewer availability Cleared 2/6/2024 JUSTIN BICOL
CPC Cleared 2/7/2024 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 2/8/2024 JEANIE LAM
HPOZ Cleared 3/8/2024 MICAELA TORRES-GIL
ZI Cleared 3/8/2024 MICAELA TORRES-GIL
Grading Pre-Inspection Cleared 3/14/2024 LUISANGEL VALENZUELA

Contact Information

Contractor Atp Development & Construction; Lic. No.: 1092130-B       ,
Contractor North By Northwest Commercial Inc; Lic. No.: 1092130-B       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/4/2024 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/4/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 4/11/2024 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 4/11/2024 Corrections Issued HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 5/6/2024 Not Ready for Inspection THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 5/10/2024 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Partial Approval THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 5/14/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 5/30/2024 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 5/30/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 6/5/2024 Approved THOMAS LOGRASSO
Insulation 6/5/2024 Approved THOMAS LOGRASSO
Drywall Nailing 6/10/2024 Corrections Issued AMY COLIN
Shower Pan 6/10/2024 Approved AMY COLIN
Drywall Nailing 6/20/2024 Approved AMY COLIN
Sewer 7/19/2024 Partial Approval THOMAS LOGRASSO
Sewer 8/12/2024 Approved THOMAS LOGRASSO
Final 8/27/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 8/27/2024 Approved THOMAS LOGRASSO
Smoke Detectors 8/27/2024 Approved THOMAS LOGRASSO
ELECTRICAL-Final 9/4/2024 Approved ROY SPAULDING
Final 9/4/2024 OK to Issue CofO ROY SPAULDING
HVAC-Final 9/4/2024 Approved ROY SPAULDING
PLUMBING-Final 9/4/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 9/4/2024 SGSOV Approved ROY SPAULDING
Service/Power Release 9/4/2024 Approved ROY SPAULDING