455 W CANYON VISTA DR 90065
Certificate Information: 455 W CANYON VISTA DR 90065
- Application / Permit
- 24014-10000-00366
- Plan Check / Job No.
- B24LA01568
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) Deck on second floor of (E) S.D.F.
- Permit Issued
- Issued on 7/5/2024
- Issuing Office
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2024 | CAROLEAN BASMA |
| Corrections Issued | 2/14/2024 | CAROLEAN BASMA |
| Plan Check Approved | 6/28/2024 | CAROLEAN BASMA |
| Issued | 7/5/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 3/6/2025 | DEROLD HAUFF |
| CofO Issued | 3/6/2025 | DEROLD HAUFF |
| Permit Finaled | 3/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/23/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 5/23/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2024 | JUSTIN BICOL |
| Specific Plan | Cleared | 6/27/2024 | ANDREA MAGANA-WITHERS |
| Grading Pre-Inspection | Cleared | 6/28/2024 | CAROLEAN BASMA |
Contact Information
| Contractor | Atlas Builders And Development Inc; Lic. No.: 1064138-B | , |
| Contractor | Atlas Builders; Lic. No.: 1064138-B | , |
| Engineer | Habibi,, Shayaan; Lic. No.: C94225 | 10535 WILSHIRE BLVD APT 1602 LOS ANGELES, CA 90024 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/1/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/8/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/8/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/15/2024 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/21/2024 | Approved | OSVALDO PARAMO |
| Wood Frame | 8/21/2024 | Approved | OSVALDO PARAMO |
| Final | 9/25/2024 | Conditional Approval | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/25/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 9/25/2024 | Approved | OSVALDO PARAMO |
| Final | 2/27/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |