4618 1/2 S ARLINGTON AVE 90043
Certificate Information: 4618 1/2 S ARLINGTON AVE 90043
- Application / Permit
- 24014-10000-00350
- Plan Check / Job No.
- B24LA01489
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Conversion and addition to (E) detached garage to ADU per LAMC 12.22 A.33 (c)-(d). Design per licensed engineer.
- Permit Issued
- Issued on 1/20/2025
- Issuing Office
- Current Status
- CofO Issued on 10/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2024 | CAROLEAN BASMA |
| Corrections Issued | 1/31/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 8/6/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/31/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 12/5/2024 | YASHAR EMAMI |
| Plan Check Approved | 12/10/2024 | DAVID CASTILLO |
| Issued | 1/20/2025 | APPLICANT |
| CofO in Progress | 10/15/2025 | LUIS CASTRO |
| Permit Finaled | 10/19/2025 | DEROLD HAUFF |
| CofO Issued | 10/19/2025 | DEROLD HAUFF |
| Permit Finaled | 10/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/15/2024 | JUSTIN BICOL |
| Address approval | Cleared | 4/17/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 4/18/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 6/10/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/20/2025 | Corrections Issued | LUIS CASTRO |
| Sewer | 2/20/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 3/28/2025 | Corrections Issued | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 4/21/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 4/21/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 7/2/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 7/2/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 7/2/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 7/2/2025 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 7/16/2025 | Corrections Issued | RONNIE MEDINA |
| ELECTRICAL-Rough | 7/18/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 7/18/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 7/18/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 7/18/2025 | Approved | LUIS CASTRO |
| Insulation | 7/24/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 7/31/2025 | Approved | RONNIE MEDINA |
| Green Building Rough | 7/31/2025 | Approved | RONNIE MEDINA |
| BUILDING-Rough-Frame | 9/2/2025 | Approved | LUIS CASTRO |
| Final | 9/2/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 9/2/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Not Ready | LUIS CASTRO |
| Smoke Detectors | 9/2/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 9/8/2025 | Corrections Issued | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 9/8/2025 | Approved | LUIS CASTRO |
| Final | 9/16/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Final | 10/14/2025 | Approved | LUIS CASTRO |
| Final | 10/14/2025 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 10/14/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 10/14/2025 | Approved | LUIS CASTRO |