5247-5247 1/2 W 9TH ST 90036
Certificate Information: 5247-5247 1/2 W 9TH ST 90036
- Application / Permit
- 24014-10000-00334
- Plan Check / Job No.
- B24LA01381
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* REMOVE GARAGE AND STORAGE EXCEPT FOR 19'-11" LINEAR FEET OF WALL ON WEST SIDE OF WALL; ADD NEW 31'-9' X 33'-10" TWO STORY (2) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g); SEE COMMENTS
- Permit Issued
- Issued on 6/7/2024
- Issuing Office
- Current Status
- CofO Issued on 6/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | SELLA BENYAMIN |
| Corrections Issued | 2/15/2024 | SELLA BENYAMIN |
| Quality Review Completed | 2/20/2024 | STEVEN KIM |
| Applicant returned to address corrections | 5/3/2024 | SELLA BENYAMIN |
| Plan Check Approved | 6/6/2024 | SELLA BENYAMIN |
| No Progress | 6/7/2024 | SELLA BENYAMIN |
| Plan Check Approved | 6/7/2024 | SELLA BENYAMIN |
| Issued | 6/7/2024 | APPLICANT |
| CofO in Progress | 6/11/2025 | JOSE MACIAS |
| Permit Finaled | 6/14/2025 | DEROLD HAUFF |
| CofO Issued | 6/14/2025 | DEROLD HAUFF |
| Permit Finaled | 6/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/5/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/9/2024 | DAVID LOPEZ |
| Hold | Cleared | 6/20/2024 | KRISTINE BUENAOBRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/2/2024 | Partial Inspection | RONNIE MINDANAO |
| Underground Mechanical | 7/15/2024 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/24/2024 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 7/24/2024 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 7/24/2024 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/30/2024 | Approved | RONNIE MINDANAO |
| Underground Mechanical | 7/31/2024 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Corrections Issued | RONNIE MINDANAO |
| Deputy Wood Construction | 8/27/2024 | Conditional Approval | RONNIE MINDANAO |
| Deputy Wood Construction | 9/3/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Wood Construction | 9/20/2024 | Conditional Approval | RONNIE MINDANAO |
| PLUMBING-Rough | 10/2/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/17/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 10/17/2024 | Corrections Issued | RONNIE MINDANAO |
| Deputy Wood Construction | 10/21/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 10/23/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/7/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/15/2024 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 11/15/2024 | Approved | RONNIE MINDANAO |
| Wood Frame | 11/15/2024 | Approved | RONNIE MINDANAO |
| Insulation | 11/19/2024 | Corrections Issued | RONNIE MINDANAO |
| Insulation | 11/21/2024 | Conditional Approval | RONNIE MINDANAO |
| Drywall Nailing | 12/3/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Drywall Nailing | 12/4/2024 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/18/2024 | Approved | RONNIE MINDANAO |
| Shower Pan | 12/18/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 12/27/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/27/2024 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 2/11/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/4/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| ELECTRICAL-Final | 4/11/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 4/11/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Final | 4/11/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 4/11/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 5/9/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 5/9/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 5/9/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 5/9/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/9/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Final | 5/19/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| ELECTRICAL-Final | 5/21/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 5/21/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 5/23/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 5/23/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 5/23/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | RONNIE MINDANAO |
| Service/Power Release | 5/23/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 5/28/2025 | Approved | JOSE MACIAS |
| Gas Test | 5/28/2025 | Approved | JOSE MACIAS |
| Service/Power Release | 5/28/2025 | Approved | JOSE MACIAS |
| Final | 6/11/2025 | OK to Issue CofO | JOSE MACIAS |