820 W 75TH ST 90044

Certificate Information: 820 W 75TH ST 90044

Application / Permit
24014-10000-00325
Plan Check / Job No.
B24LA01329
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: 36'1" x 17'6" ADDITION TO THE REAR OF (E) SFD.
Permit Issued
Issued on 6/6/2024
Issuing Office
Current Status
CofO Issued on 4/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2024 APPLICANT
Assigned to Plan Check Engineer 1/31/2024 MIROOSH KHACHATOORIAN
Corrections Issued 2/1/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 5/23/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 6/1/2024 ISIS ARGUETA
Issued 6/6/2024 APPLICANT
CofO in Progress 4/16/2025 JOHN QUINTANILLA
Permit Finaled 4/17/2025 DEROLD HAUFF
CofO Issued 4/17/2025 DEROLD HAUFF
Permit Finaled 4/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/6/2024 ARNULFO CHAMU
Sewer availability Cleared 2/6/2024 ARNULFO CHAMU
Low Impact Development (LID) Cleared 5/15/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 5/20/2024 JEANIE LAM

Contact Information

Architect Gutierrez,, Juan Antonio; Lic. No.: C33231 15622 PATRONELLA AVENUE      GARDENA, CA 90249
Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/2/2024 Approved MICHAEL LEWIS
Deputy Drilled-In Anchors 8/8/2024 Conditional Approval MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 8/19/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/19/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/19/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 9/19/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Approved SABAS ALONSO
Green Building Rough 9/19/2024 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 9/27/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 9/27/2024 Approved MICHAEL LEWIS
Green Building Rough 9/27/2024 Approved MICHAEL LEWIS
HVAC-Rough 9/27/2024 Partial Inspection MICHAEL LEWIS
Interior/Exterior Lathing 9/27/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 9/27/2024 Approved MICHAEL LEWIS
Sewer 9/27/2024 Approved MICHAEL LEWIS
Insulation 10/2/2024 Approved JOHN QUINTANILLA
Underground Mechanical 10/2/2024 Approved JOHN QUINTANILLA
Drywall Nailing 10/11/2024 Approved ALEX COLIN
HVAC-Final 11/15/2024 Approved MICHAEL LEWIS
PLUMBING-Final 11/15/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 11/20/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 12/23/2024 Approved JOHN QUINTANILLA
Final 12/23/2024 Partial Approval JOHN QUINTANILLA
Footing/Foundation/Slab 12/23/2024 Approved JOHN QUINTANILLA
Green Building Final 12/23/2024 Approved JOHN QUINTANILLA
HVAC-Final 12/23/2024 Approved JOHN QUINTANILLA
PLUMBING-Final 12/23/2024 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 12/23/2024 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 12/23/2024 Approved JOHN QUINTANILLA
Final 4/9/2025 Corrections Issued JOHN QUINTANILLA
Final 4/14/2025 OK to Issue CofO JOHN QUINTANILLA
Service/Power Release 4/15/2025 Approved JOHN QUINTANILLA