6750 S ARLINGTON AVE 90043
Certificate Information: 6750 S ARLINGTON AVE 90043
- Application / Permit
- 24014-10000-00324
- Plan Check / Job No.
- B24LA01320
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Detached 1-Story Garage Conversion to ADU w/Addition per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- Issued on 3/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2024 | DAVID CASTILLO |
| Corrections Issued | 1/29/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/30/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 2/21/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 3/5/2025 | DAVID CASTILLO |
| Plan Check Approved | 3/16/2025 | DAVID CASTILLO |
| Issued | 3/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 3/11/2024 | JUSTIN BICOL |
| Construction within easement | Cleared | 7/7/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 2/4/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/5/2025 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/7/2025 | Approved | WAYNE REGESTER |
| Footing/Foundation/Slab | 4/7/2025 | Approved | WAYNE REGESTER |
| Underground Mechanical | 4/11/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Wood Frame | 4/11/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Wood Frame | 4/15/2025 | Partial Approval | JOHN QUINTANILLA |
| Wood Frame | 4/17/2025 | Approved | WAYNE REGESTER |
| Deputy Wood Construction | 4/30/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 4/30/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 4/30/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Rough | 4/30/2025 | Approved | WAYNE REGESTER |
| Wood Frame | 4/30/2025 | Approved | WAYNE REGESTER |
| Insulation | 5/6/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 5/6/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 5/8/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 3/26/2026 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 3/26/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 3/26/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 3/26/2026 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 3/26/2026 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 3/26/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 3/26/2026 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 3/26/2026 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 4/28/2026 | No Access for Inspection | SALVADOR MARTINEZ |
| Final | 4/28/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 4/28/2026 | No Access for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Final | 4/28/2026 | No Access for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 4/28/2026 | No Access for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 5/13/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 5/13/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 5/13/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 5/13/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Smoke Detectors | 5/13/2026 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 5/21/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 5/21/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 5/21/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 5/21/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Smoke Detectors | 5/21/2026 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 5/27/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 5/27/2026 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 5/27/2026 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 5/27/2026 | Approved | NICHOLAS LOPEZ |
| Final | 6/2/2026 | Conditional Approval | SALVADOR MARTINEZ |
| Service/Power Release | 6/2/2026 | Approved | SALVADOR MARTINEZ |