6701 W COLGATE AVE 90048

Certificate Information: 6701 W COLGATE AVE 90048

Application / Permit
24014-10000-00323
Plan Check / Job No.
B24LA01313
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION TO FRONT (10' 9" X 17'7") AND REAR (8'7" X 11' 3" OF HOUSE, REMODEL HOUSE TO CHANGE FROM 2-BED 2-BATH TO 4 BEDROOM, ADD 1-BATH, 1-POWDER ROOM, RELOCATE KITCHEN TO NEW ADDITION.
Permit Issued
Issued on 3/19/2024
Issuing Office
Current Status
CofO Issued on 4/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2024 APPLICANT
Assigned to Plan Check Engineer 1/26/2024 NGHI SU
Corrections Issued 1/27/2024 NGHI SU
Building Plans Picked Up 2/14/2024 APPLICANT
Plan Check Approved 3/19/2024 YAQUB MIRZA
Issued 3/19/2024 APPLICANT
CofO in Progress 3/27/2025 EVAN COOPER
CofO Issued 4/4/2025 RICHARD STEINBACH
Permit Finaled 4/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/21/2024 DAVID LOPEZ
Sewer availability Cleared 2/21/2024 DAVID LOPEZ
CPC Cleared 3/4/2024 RYAN LY
ZA Case Cleared 3/4/2024 RYAN LY
ZI Cleared 3/4/2024 RYAN LY
Eng Process Fee Ord 176,300 Cleared 3/19/2024 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/30/2024 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 5/30/2024 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 5/30/2024 Approved MEL KHACHATOURIAN
METHANE-Barrier 5/30/2024 Approved MEL KHACHATOURIAN
METHANE-Subgrade 5/30/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 5/30/2024 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval MEL KHACHATOURIAN
Underground Mechanical 6/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 6/13/2024 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 6/13/2024 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Approved MEL KHACHATOURIAN
Rough-Elec/Plmb/HVAC 7/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 9/4/2024 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Not Ready for Inspection ARAM AVEDISIAN
Green Building Rough 9/4/2024 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 9/4/2024 Partial Approval ARAM AVEDISIAN
METHANE-Rough 9/4/2024 Approved ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 9/4/2024 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 9/9/2024 Corrections Issued SEAN HAUPT
Interior/Exterior Lathing 9/9/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 9/12/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 9/12/2024 Approved ARAM AVEDISIAN
Green Building Rough 9/12/2024 Approved ARAM AVEDISIAN
HVAC-Rough 9/12/2024 Approved ARAM AVEDISIAN
PLUMBING-Rough 9/12/2024 Approved ARAM AVEDISIAN
Insulation 9/18/2024 Approved REGINA MENDEZ
Drywall Nailing 10/7/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 10/7/2024 Approved MEL KHACHATOURIAN
Shower Pan 10/7/2024 Approved MEL KHACHATOURIAN
Final 2/21/2025 Corrections Issued MEL KHACHATOURIAN
Green Building Final 2/21/2025 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Not Ready MEL KHACHATOURIAN
Smoke Detectors 2/21/2025 Not Ready for Inspection MEL KHACHATOURIAN
Final 3/25/2025 Conditional Approval EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/25/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 3/25/2025 Approved EVAN COOPER
Final 3/27/2025 OK to Issue CofO EVAN COOPER