6701 W COLGATE AVE 90048
Certificate Information: 6701 W COLGATE AVE 90048
- Application / Permit
- 24014-10000-00323
- Plan Check / Job No.
- B24LA01313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION TO FRONT (10' 9" X 17'7") AND REAR (8'7" X 11' 3" OF HOUSE, REMODEL HOUSE TO CHANGE FROM 2-BED 2-BATH TO 4 BEDROOM, ADD 1-BATH, 1-POWDER ROOM, RELOCATE KITCHEN TO NEW ADDITION.
- Permit Issued
- Issued on 3/19/2024
- Issuing Office
- Current Status
- CofO Issued on 4/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2024 | NGHI SU |
| Corrections Issued | 1/27/2024 | NGHI SU |
| Building Plans Picked Up | 2/14/2024 | APPLICANT |
| Plan Check Approved | 3/19/2024 | YAQUB MIRZA |
| Issued | 3/19/2024 | APPLICANT |
| CofO in Progress | 3/27/2025 | EVAN COOPER |
| CofO Issued | 4/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/21/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 2/21/2024 | DAVID LOPEZ |
| CPC | Cleared | 3/4/2024 | RYAN LY |
| ZA Case | Cleared | 3/4/2024 | RYAN LY |
| ZI | Cleared | 3/4/2024 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2024 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/30/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/30/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/30/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 5/30/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 5/30/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/30/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 6/11/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/13/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/13/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Approved | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 7/12/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 9/4/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 9/4/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/4/2024 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Rough | 9/4/2024 | Approved | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 9/4/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/9/2024 | Corrections Issued | SEAN HAUPT |
| Interior/Exterior Lathing | 9/9/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/12/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/12/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/12/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 9/12/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/12/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 9/18/2024 | Approved | REGINA MENDEZ |
| Drywall Nailing | 10/7/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 10/7/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 10/7/2024 | Approved | MEL KHACHATOURIAN |
| Final | 2/21/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 2/21/2025 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 2/21/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 3/25/2025 | Conditional Approval | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 3/25/2025 | Approved | EVAN COOPER |
| Final | 3/27/2025 | OK to Issue CofO | EVAN COOPER |