10458 W WILKINS AVE 90024
Certificate Information: 10458 W WILKINS AVE 90024
- Application / Permit
- 24014-10000-00322
- Plan Check / Job No.
- B24LA01311
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan Remodel of first floor and ground floor addition to existing 2 story SFD
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2024 | JOHNPAUL ISIP |
| Corrections Issued | 1/31/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 3/7/2024 | DAVID CASTILLO |
| Plan Check Approved | 7/12/2024 | DAVID CASTILLO |
| Issued | 7/17/2024 | APPLICANT |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
| CofO Issued | 3/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/15/2024 | ANDREA SAINT-ANTONIN |
| Metro Rail approval | Cleared | 2/16/2024 | JENNIFER SU |
| Specific Plan | Cleared | 2/20/2024 | PEDRO AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2024 | ANDREA SAINT-ANTONIN |
| Grading Pre-Inspection | Cleared | 3/7/2024 | JOHNPAUL ISIP |
Contact Information
| Architect | Ryder,, Derek Thomas; Lic. No.: C32847 | 4111 GLENALBYN DRIVE LOS ANGELES, CA 90065 |
| Contractor | Home Front Build Inc; Lic. No.: 962293-B | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/5/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/5/2024 | Approved | CHRISTOPHER WILSON |
| METHANE-Barrier | 8/5/2024 | Approved | CHRISTOPHER WILSON |
| METHANE-Subgrade | 8/5/2024 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 8/13/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 8/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 10/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/15/2024 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/18/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/18/2024 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 10/18/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 10/18/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/18/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 10/23/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/23/2024 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 10/25/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 10/25/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/4/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 11/6/2024 | Approved | STEPHANIE SWANSON |
| Final | 2/21/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 2/21/2025 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 2/21/2025 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 2/21/2025 | Approved | STEPHANIE SWANSON |
| Final | 3/4/2025 | Partial Approval | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/4/2025 | SGSOV Approved | CARLOS MATAMOROS |
| Final | 3/6/2025 | Conditional Approval | STEPHANIE SWANSON |