3002 S 11TH AVE 90018
Certificate Information: 3002 S 11TH AVE 90018
- Application / Permit
- 24014-10000-00321
- Plan Check / Job No.
- B24LA01307
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF 92 SF. CONVERT (E) DETACHED GARAGE TO NEW ADU PER GCS 65852.2(e)(1)(A) AND STORAGE.
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 3/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2024 | NGHI SU |
| Corrections Issued | 1/27/2024 | NGHI SU |
| Building Plans Picked Up | 4/2/2024 | APPLICANT |
| Plan Check Approved | 4/4/2024 | ALEXANDER JOO |
| Issued | 4/10/2024 | APPLICANT |
| CofO in Progress | 2/13/2025 | JOHN QUINTANILLA |
| No Progress | 3/30/2025 | DEROLD HAUFF |
| CofO in Progress | 3/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2024 | ANTHONY TRAN |
| Roof/Waste drainage to street | Cleared | 3/6/2024 | ANTHONY TRAN |
| Sewer availability | Cleared | 3/6/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | DAVID VO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/10/2024 | Conditional Approval | JUSTIN HAWLEY |
| Underground Mechanical | 5/13/2024 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 5/15/2024 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 6/3/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Partial Approval | JUSTIN HAWLEY |
| Gas Test | 6/26/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 6/26/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 8/16/2024 | Corrections Issued | JUSTIN HAWLEY |
| Shower Pan | 8/20/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/29/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 8/29/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 8/29/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 9/3/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/3/2024 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 9/9/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Final | 11/5/2024 | Corrections Issued | JUSTIN HAWLEY |
| Gas Test | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Green Building Final | 11/5/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 11/5/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Final | 11/5/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 11/5/2024 | Approved | JUSTIN HAWLEY |
| Final | 11/19/2024 | OK to Issue CofO | JOHN QUINTANILLA |
| Green Building Final | 11/19/2024 | Approved | JOHN QUINTANILLA |