16120 S DENVER AVE 90248
Certificate Information: 16120 S DENVER AVE 90248
- Application / Permit
- 24014-10000-00318
- Plan Check / Job No.
- B23LA24799
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert Detached Storage to Accessory Dwelling Unit w/ Addition per LAMC 12.22 A.33 (c)-(d) . Work per Engineerd Design .
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Current Status
- CofO Issued on 12/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 2/6/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 5/21/2024 | NGHI SU |
| Applicant returned to address corrections | 6/14/2024 | NGHI SU |
| Applicant returned to address corrections | 6/25/2024 | KELVIN CHUONG |
| Plan Check Approved | 6/27/2024 | GEORGE ALVAREZ |
| Issued | 7/16/2024 | APPLICANT |
| CofO in Progress | 12/16/2025 | BEN MOLSTAD |
| Permit Finaled | 12/17/2025 | ANSON MAGLASANG |
| Permit Finaled | 12/17/2025 | ANSON MAGLASANG |
| CofO Issued | 12/17/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 4/25/2024 | ERIK BEASLEY |
| Low Impact Development (LID) | Cleared | 6/18/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/20/2024 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiang,, Tzuu Pien; Lic. No.: C72618 | 18295 AGUIRO STREET ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2024 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/16/2025 | No Access for Inspection | BEN MOLSTAD |
| Final | 4/16/2025 | No Access for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 4/16/2025 | No Access for Inspection | BEN MOLSTAD |
| Green Building Final | 4/16/2025 | No Access for Inspection | BEN MOLSTAD |
| Green Building Rough | 4/16/2025 | No Access for Inspection | BEN MOLSTAD |
| MERV13>=Final | 4/16/2025 | No Access for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 4/16/2025 | No Access for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/16/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 4/16/2025 | No Access for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/3/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 12/3/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 12/3/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 12/3/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 12/3/2025 | Approved | BEN MOLSTAD |
| Green Building Rough | 12/3/2025 | Approved | BEN MOLSTAD |
| HVAC-Final | 12/3/2025 | Approved | BEN MOLSTAD |
| MERV13>=Final | 12/3/2025 | Approved | BEN MOLSTAD |
| MERV13>=Rough | 12/3/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 12/3/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 12/3/2025 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 12/3/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 12/5/2025 | Approved | BEN MOLSTAD |
| Final | 12/5/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 12/5/2025 | Approved | BEN MOLSTAD |
| HVAC-Final | 12/5/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 12/5/2025 | Approved | BEN MOLSTAD |
| Final | 12/11/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 12/16/2025 | OK to Issue CofO | BEN MOLSTAD |