13338 W MCCORMICK ST 91401

Certificate Information: 13338 W MCCORMICK ST 91401

Application / Permit
24014-10000-00302
Plan Check / Job No.
B24LA01223
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan ADDITION AND MAJOR REMODEL TO (E) 1-STORY SFD. NOW A 2-STORY SFD WITH ATTACHED GARAGE. EQUIPPED WITH FIRE SPRINKLERS NFPA 13D THROUGH OUT.
Permit Issued
Issued on 7/25/2024
Issuing Office
Current Status
CofO Issued on 7/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 ADRIANA LOPEZ
Corrections Issued 1/31/2024 ADRIANA LOPEZ
Quality Review Completed 2/7/2024 GARO TELMI
Applicant returned to address corrections 7/10/2024 ADRIANA LOPEZ
Plan Check Approved 7/24/2024 ADRIANA LOPEZ
Issued 7/25/2024 APPLICANT
CofO in Progress 6/23/2025 MISAEL ESPARZA
CofO in Progress 6/24/2025 MISAEL ESPARZA
Permit Finaled 7/30/2025 RUBEN SALAS
CofO Issued 7/30/2025 RUBEN SALAS
Permit Finaled 7/30/2025 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 2/13/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/14/2024 LEE GUILBEAUX
Sewer availability Cleared 2/14/2024 LEE GUILBEAUX
Trees in Parkway Cleared 2/29/2024 ADALBERTO VERA
Low Impact Development (LID) Cleared 3/20/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 3/20/2024 LEE GUILBEAUX

Contact Information

Contractor Gt Remodeling Inc; Lic. No.: 1091310-B       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/7/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 8/26/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/4/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/6/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/11/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Partial Approval MISAEL ESPARZA
Deputy Wood Construction 10/24/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval MISAEL ESPARZA
Gas Test 11/7/2024 Partial Approval MISAEL ESPARZA
HVAC-Rough 11/7/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 11/7/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 12/4/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 12/4/2024 Approved MISAEL ESPARZA
Green Building Rough 12/4/2024 Approved MISAEL ESPARZA
HVAC-Rough 12/4/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/4/2024 Partial Approval MISAEL ESPARZA
Shower Pan 12/4/2024 Corrections Issued MISAEL ESPARZA
Wood Frame 12/4/2024 Approved MISAEL ESPARZA
Insulation 12/16/2024 Conditional Approval MISAEL ESPARZA
Shower Pan 12/16/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/23/2024 Approved MISAEL ESPARZA
Drywall Nailing 1/2/2025 Approved MISAEL ESPARZA
Gas Test 3/21/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Final 5/14/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved JAVIER RAMOS JR
Final 5/23/2025 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 5/23/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 5/23/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 5/23/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 5/28/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 6/16/2025 Corrections Issued MISAEL ESPARZA
Final 6/16/2025 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 6/16/2025 Approved MISAEL ESPARZA
Green Building Final 6/16/2025 Approved MISAEL ESPARZA
HVAC-Final 6/16/2025 Approved MISAEL ESPARZA
Smoke Detectors 6/16/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/18/2025 Approved MISAEL ESPARZA
Final 6/18/2025 OK to Issue CofO MISAEL ESPARZA
Final 6/24/2025 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 6/24/2025 Approved MISAEL ESPARZA