1640 1/4-1/2 W 80TH ST 90047

Certificate Information: 1640 1/4-1/2 W 80TH ST 90047

Application / Permit
24014-10000-00278
Plan Check / Job No.
B24LA01155
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN NEW 38' X 38' THREE STORY DUPLEX WITH ATTACHED ACCEESSORY DWELLING UNIT AS PER LAMC 12.22 A.33(c) and (e), NFPA-13D FIRE SPRINKLERS REQURIED THROUGHOUT, NO REQUIRED PARKING PER AB2097, ALL WORK PER ENGINEERING - SEE COMMENTS
Permit Issued
Issued on 10/20/2025
Issuing Office
Current Status
Issued on 10/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/23/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 RARES BODEA
Corrections Issued 2/16/2024 RARES BODEA
Quality Review Completed 2/20/2024 STEVEN KIM
Applicant returned to address corrections 6/24/2024 RARES BODEA
Applicant returned to address corrections 10/2/2024 RARES BODEA
Plan Check Approved 10/3/2024 RARES BODEA
Issued 10/20/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/3/2024 JUSTIN BICOL
ZI Cleared 7/12/2024 DANIEL CORONADO
Frnt yard landscape/Water mgmt Cleared 7/15/2024 JAZMIN ROQUE
DAS Clearance Cleared 7/18/2024 RARES BODEA
Low Impact Development (LID) Cleared 8/26/2024 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 8/27/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 8/28/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 9/4/2024 JOHN CONNEALLY
Construction near power lines Cleared 9/13/2024 RIDWAN HARDY
Sewer availability Cleared 9/23/2024 JUSTIN BICOL

Contact Information

Contractor Jcs General Construction Inc; Lic. No.: 1045869-B 1638 WEST 80TH STREET      LOS ANGELES, CA 90047
Engineer Saoud,, Tarik; Lic. No.: C81282 616 N SWEETZER AVE #205      LOS ANGELES, CA 90048

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/15/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 12/17/2025 Partial Approval SALVADOR MARTINEZ
Special/Order Compliance 12/17/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 12/29/2025 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 1/14/2026 Not Ready for Inspection SALVADOR MARTINEZ
Special/Order Compliance 1/14/2026 Corrections Issued SALVADOR MARTINEZ
Deputy Drilled-In Anchors 1/23/2026 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 1/26/2026 Not Ready for Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 2/5/2026 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 2/11/2026 Approved BRENDAN MORELLI
Deputy Steel/Welding 3/2/2026 Conditional Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/2/2026 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/24/2026 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 5/7/2026 Corrections Issued SALVADOR MARTINEZ
Deputy Wood Construction 6/4/2026 Conditional Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 6/4/2026 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/16/2026 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 6/26/2026 Partial Inspection SALVADOR MARTINEZ