10819 N BATON ROUGE AVE 91326
Certificate Information: 10819 N BATON ROUGE AVE 91326
- Application / Permit
- 24014-10000-00275
- Plan Check / Job No.
- B24LA01138
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Single-story ground floor addition to (E) SFD with ATT. garage
- Permit Issued
- Issued on 4/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 2/22/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 2/23/2024 | KEN GILL |
| Building Plans Picked Up | 3/18/2024 | APPLICANT |
| Plan Check Approved | 4/9/2024 | GEORGE JOLAKIAN |
| Issued | 4/29/2024 | APPLICANT |
| CofO in Progress | 5/21/2025 | DAVID SCANTLIN |
| Permit Finaled | 2/27/2026 | JOHN JANSON |
| CofO Issued | 2/27/2026 | JOHN JANSON |
| Permit Finaled | 2/27/2026 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/2/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 3/27/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 3/28/2024 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 4/9/2024 | GEORGE JOLAKIAN |
| Grading Pre-Inspection | Cleared | 4/9/2024 | GEORGE JOLAKIAN |
Contact Information
| Contractor | Victor King Construction; Lic. No.: 701175-B | 6315 BUCKLER AVE LOS ANGELES, CA 90043 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/16/2024 | Conditional Approval | DAVID SCANTLIN |
| Sewer | 5/20/2024 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 5/23/2024 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/23/2024 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 5/23/2024 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 7/29/2024 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 7/29/2024 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 7/29/2024 | Approved | DAVID SCANTLIN |
| Wood Frame | 7/29/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 8/28/2024 | Approved | DAVID SCANTLIN |
| Green Building Rough | 8/28/2024 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 8/28/2024 | Partial Approval | DAVID SCANTLIN |
| Shower Pan | 8/28/2024 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 8/28/2024 | Approved | SCOTT SOBEL |
| Insulation | 9/10/2024 | Partial Approval | DAVID SCANTLIN |
| Special/Order Compliance | 9/10/2024 | Approved | SCOTT SOBEL |
| Drywall Nailing | 9/24/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 10/7/2024 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/7/2024 | Approved | KRISTEN CAUSEY |
| Final | 5/9/2025 | Not Ready for Inspection | KRISTEN CAUSEY |
| Final | 5/16/2025 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 5/16/2025 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 5/16/2025 | Approved | DAVID SCANTLIN |