4823 N LEDGE AVE 91601

Certificate Information: 4823 N LEDGE AVE 91601

Application / Permit
24014-10000-00265
Plan Check / Job No.
B24LA01084
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition to the front of and interior remodel to (E) two story SFD
Permit Issued
Issued on 5/29/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 JOSE VELAZQUEZ
Corrections Issued 1/25/2024 JOSE VELAZQUEZ
Building Plans Picked Up 1/25/2024 APPLICANT
Applicant returned to address corrections 3/28/2024 LUKE GONZALES
Plan Check Approved 4/12/2024 ALEXANDER JOO
Issued 5/29/2024 APPLICANT
CofO in Progress 7/25/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 8/28/2025 RUBEN SALAS
CofO Issued 8/28/2025 RUBEN SALAS
Permit Finaled 8/28/2025 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 2/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/15/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 3/22/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 3/26/2024 LEE GUILBEAUX
Miscellaneous Cleared 4/8/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 7/29/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 10/1/2024 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 10/30/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 10/30/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 11/4/2024 Approved JOSE AVILA
PLUMBING-Rough 11/4/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 11/13/2024 Corrections Issued JOSE AVILA
HVAC-Rough 11/19/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 11/21/2024 Approved JOSE AVILA
Green Building Rough 11/21/2024 Approved JOSE AVILA
HVAC-Rough 11/21/2024 Approved JOSE AVILA
Interior/Exterior Lathing 12/3/2024 Partial Approval JACK KARGODORIAN
Insulation 12/10/2024 Approved JOSE AVILA
Drywall Nailing 12/17/2024 Approved JOSE AVILA
Shower Pan 1/8/2025 Approved JOSE AVILA
PLUMBING-Final 2/11/2025 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Final 2/26/2025 Approved JOSE AVILA
Final 2/26/2025 Corrections Issued JOSE AVILA
Green Building Final 2/26/2025 Approved JOSE AVILA
HVAC-Final 2/26/2025 Approved JOSE AVILA
PLUMBING-Final 2/26/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Not Ready JOSE AVILA
Smoke Detectors 2/26/2025 Approved JOSE AVILA
Final 3/4/2025 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/4/2025 SGSOV Approved JOSE AVILA
Final 7/24/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ