1987 N LUCILE AVE 90039
Certificate Information: 1987 N LUCILE AVE 90039
- Application / Permit
- 24014-10000-00263
- Plan Check / Job No.
- B24LA01073
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN PROPOSED 2-STORY ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Current Status
- Issued on 8/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | RAPHAEL ROSAS |
| Corrections Issued | 2/15/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 2/15/2024 | STEVEN KIM |
| Applicant returned to address corrections | 5/13/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/18/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 8/23/2024 | RAPHAEL ROSAS |
| Issued | 8/29/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/17/2024 | CELINA MORENO |
| Public Works-Highway Ded. | Cleared | 2/17/2024 | CELINA MORENO |
| Public Works-Open Permits | Cleared | 2/17/2024 | CELINA MORENO |
| Public Works-Sewers | Cleared | 2/17/2024 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 2/20/2024 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 2/20/2024 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 2/20/2024 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 2/20/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2024 | TREVOR QUAN |
| ZA Case | Cleared | 2/20/2024 | RYAN LY |
| Distance to fire station | Cleared | 7/22/2024 | RUEL COLE |
| Hydrant and Access approval | Cleared | 7/22/2024 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 7/22/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/25/2024 | JUSTIN BICOL |
| BHO/Hillside ordinance | Cleared | 8/6/2024 | AMBER CAMPBELL |
| GPI Written Notices | Cleared | 8/23/2024 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 8/23/2024 | RAPHAEL ROSAS |
Contact Information
| Contractor | Lightning Construction & Design Inc; Lic. No.: 951122-B | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Hoek,, Johan; Lic. No.: EG2544 | 10369 SILVERSTON AVE TUJUNGA, CA 91042 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 2/4/2025 | Approved | ENRIQUE MIRELES |
| Deputy Grading | 2/5/2025 | Approved | ENRIQUE MIRELES |
| Piling/Pier/Caisson | 4/2/2025 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 4/16/2025 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/16/2025 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 4/18/2025 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/25/2025 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 5/5/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/12/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/19/2025 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/28/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 1/30/2026 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/11/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 2/11/2026 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/13/2026 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/13/2026 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/13/2026 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/26/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 3/26/2026 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/26/2026 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/17/2026 | Approved | ENRIQUE MIRELES |
| Insulation | 4/17/2026 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/24/2026 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/5/2026 | Approved | ENRIQUE MIRELES |
| Shower Pan | 5/5/2026 | Approved | ENRIQUE MIRELES |