3218 S WOODBINE ST 90064

Certificate Information: 3218 S WOODBINE ST 90064

Application / Permit
24014-10000-00258
Plan Check / Job No.
B24LA01047
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Major remodel of existing SFD with attached gargae. New 1st and 2nd story addition.
Permit Issued
Issued on 11/11/2024
Issuing Office
Current Status
CofO Issued on 2/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 MARCELA FRANQUEZ
Corrections Issued 4/25/2024 MARCELA FRANQUEZ
Quality Review Completed 5/1/2024 GARO TELMI
Applicant returned to address corrections 7/15/2024 MARCELA FRANQUEZ
Plan Check Approved 8/26/2024 MARCELA FRANQUEZ
Issued 11/11/2024 APPLICANT
CofO in Progress 2/17/2026 WILBER ROSALES
Permit Finaled 2/24/2026 RICHARD STEINBACH
CofO Issued 2/24/2026 RICHARD STEINBACH
Permit Finaled 2/24/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/2/2024 BRENDEN HAWK
Eng Process Fee Ord 176,300 Cleared 7/10/2024 BRENDEN HAWK
Sewer availability Cleared 7/10/2024 BRENDEN HAWK
GPI Written Notices Cleared 7/12/2024 MARCELA FRANQUEZ
Grading Pre-Inspection Cleared 7/12/2024 MARCELA FRANQUEZ

Contact Information

Contractor Green Roomers Inc; Lic. No.: 927982-B       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2025 Approved BOBBY KEY
PLUMBING-Rough 2/28/2025 Partial Approval ARAM AVEDISIAN
Wood Frame 2/28/2025 Partial Approval ARAM AVEDISIAN
Insulation 3/3/2025 Partial Approval REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Corrections Issued ARAM AVEDISIAN
Deputy Wood Construction 4/3/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 6/16/2025 Approved ASHLEY THOMPSON
PLUMBING-Rough 6/16/2025 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Partial Approval ARAM AVEDISIAN
HVAC-Rough 6/17/2025 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 6/27/2025 Corrections Issued ASHLEY THOMPSON
Green Building Rough 6/27/2025 Approved ASHLEY THOMPSON
HVAC-Rough 6/27/2025 Not Ready for Inspection ASHLEY THOMPSON
Verify Sprinkler Sign Off 6/27/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 7/8/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 7/8/2025 Approved ASHLEY THOMPSON
PLUMBING-Rough 7/8/2025 Approved ASHLEY THOMPSON
Insulation 8/1/2025 Corrections Issued STEPHANIE SWANSON
Insulation 8/4/2025 Approved STEPHANIE SWANSON
Drywall Nailing 8/7/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 8/13/2025 Partial Approval ASHLEY THOMPSON
Shower Pan 8/13/2025 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 8/14/2025 Approved ASHLEY THOMPSON
Shower Pan 8/14/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 1/20/2026 Approved ASHLEY THOMPSON
ELECTRICAL-Final 1/20/2026 Corrections Issued ASHLEY THOMPSON
Green Building Final 1/20/2026 Not Ready for Inspection ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 1/20/2026 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 1/20/2026 Approved ASHLEY THOMPSON
Special/Order Compliance 1/20/2026 Partial Inspection DAKOTA LOW
ELECTRICAL-Final 1/29/2026 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Final 1/29/2026 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 2/4/2026 Not Ready for Inspection DANIEL VERA
Final 2/4/2026 Not Ready for Inspection DANIEL VERA
HVAC-Final 2/4/2026 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 2/4/2026 Not Ready for Inspection DANIEL VERA
Service/Power Release 2/4/2026 Not Ready for Inspection DANIEL VERA
HVAC-Final 2/10/2026 Approved RYAN SALAZAR
PLUMBING-Final 2/10/2026 Approved RYAN SALAZAR
ELECTRICAL-Final 2/13/2026 Approved WILBER ROSALES
Final 2/13/2026 OK to Issue CofO WILBER ROSALES
Green Building Final 2/13/2026 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved WILBER ROSALES
Service/Power Release 2/23/2026 Approved DAVID FEILER