3218 S WOODBINE ST 90064
Certificate Information: 3218 S WOODBINE ST 90064
- Application / Permit
- 24014-10000-00258
- Plan Check / Job No.
- B24LA01047
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Major remodel of existing SFD with attached gargae. New 1st and 2nd story addition.
- Permit Issued
- Issued on 11/11/2024
- Issuing Office
- Current Status
- CofO Issued on 2/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 4/25/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 5/1/2024 | GARO TELMI |
| Applicant returned to address corrections | 7/15/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 8/26/2024 | MARCELA FRANQUEZ |
| Issued | 11/11/2024 | APPLICANT |
| CofO in Progress | 2/17/2026 | WILBER ROSALES |
| Permit Finaled | 2/24/2026 | RICHARD STEINBACH |
| CofO Issued | 2/24/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/24/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/2/2024 | BRENDEN HAWK |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2024 | BRENDEN HAWK |
| Sewer availability | Cleared | 7/10/2024 | BRENDEN HAWK |
| GPI Written Notices | Cleared | 7/12/2024 | MARCELA FRANQUEZ |
| Grading Pre-Inspection | Cleared | 7/12/2024 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Green Roomers Inc; Lic. No.: 927982-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/28/2025 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 2/28/2025 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 3/3/2025 | Partial Approval | REGINA MENDEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Wood Construction | 4/3/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/16/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 6/16/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 6/17/2025 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/27/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 6/27/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 6/27/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 6/27/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 7/8/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 7/8/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 7/8/2025 | Approved | ASHLEY THOMPSON |
| Insulation | 8/1/2025 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 8/4/2025 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 8/7/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/13/2025 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 8/13/2025 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/14/2025 | Approved | ASHLEY THOMPSON |
| Shower Pan | 8/14/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/20/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/20/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 1/20/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 1/20/2026 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 1/20/2026 | Partial Inspection | DAKOTA LOW |
| ELECTRICAL-Final | 1/29/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Final | 1/29/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 2/4/2026 | Not Ready for Inspection | DANIEL VERA |
| Final | 2/4/2026 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 2/4/2026 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 2/4/2026 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 2/4/2026 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 2/10/2026 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 2/10/2026 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 2/13/2026 | Approved | WILBER ROSALES |
| Final | 2/13/2026 | OK to Issue CofO | WILBER ROSALES |
| Green Building Final | 2/13/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 2/23/2026 | Approved | DAVID FEILER |