3816 W GRIFFITH VIEW DR 90039
Certificate Information: 3816 W GRIFFITH VIEW DR 90039
- Application / Permit
- 24014-10000-00253
- Plan Check / Job No.
- B24LA01024
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and interior remodel at kitchen of (E) SFD, demo (E) rear porch and add new rear covered porch
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2024 | ALEXANDER JOO |
| Corrections Issued | 1/24/2024 | ALEXANDER JOO |
| Building Plans Picked Up | 1/26/2024 | APPLICANT |
| Applicant returned to address corrections | 3/14/2024 | MINA HABILI |
| Plan Check Approved | 4/9/2024 | MINA HABILI |
| Issued | 7/17/2024 | APPLICANT |
| CofO in Progress | 4/14/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
| CofO Issued | 4/17/2025 | DEROLD HAUFF |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/8/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2024 | JUSTIN BICOL |
Contact Information
| Architect | Joslin,, Timothy C; Lic. No.: C33261 | 1172 N HACIENDA PLACE # 20 WEST HOLLYWOOD, CA 90069 |
| Contractor | Recal Construction Inc; Lic. No.: 1025668-B | 7311 MATILIJA AVE VAN NUYS, CA 91405 |
| Engineer | Shah,, Kamal Rajendra; Lic. No.: C46200 | 28611 HASKELL CANYON RD SANTA CLARITA, CA 91390 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/7/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/14/2024 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/15/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Partial Approval | THOMAS LOGRASSO |
| Gas Test | 9/17/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/17/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 10/10/2024 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/29/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Rough | 10/29/2024 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 10/29/2024 | Approved | BRENDAN MORELLI |
| Green Building Rough | 10/29/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 10/29/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 11/18/2024 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 11/18/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 11/18/2024 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/18/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 11/20/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 11/21/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 11/21/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/10/2025 | Approved | NICHOLAS LOPEZ |
| Final | 4/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 4/10/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 4/10/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 4/10/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 4/10/2025 | Approved | NICHOLAS LOPEZ |
| Final | 4/14/2025 | OK to Issue CofO | NICHOLAS LOPEZ |