13944 W ADDISON ST 91423
Certificate Information: 13944 W ADDISON ST 91423
- Application / Permit
- 24014-10000-00241
- Plan Check / Job No.
- B24LA00977
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* GROUND FLOOR ADDITION, ATTACHED 2-CAR GARAGE ADDITION, AND MAJOR REMODEL TO (E) 1-STORY SFD. NFPA 13D.
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Current Status
- CofO Issued on 5/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | VIVIAN LAO |
| Corrections Issued | 2/9/2024 | VIVIAN LAO |
| Quality Review Completed | 2/9/2024 | GARO TELMI |
| Applicant returned to address corrections | 3/21/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 4/3/2024 | VIVIAN LAO |
| Plan Check Approved | 4/19/2024 | VIVIAN LAO |
| Issued | 7/17/2024 | APPLICANT |
| CofO in Progress | 5/2/2025 | MISAEL ESPARZA |
| Permit Finaled | 5/12/2025 | RUBEN SALAS |
| CofO Issued | 5/12/2025 | RUBEN SALAS |
| Permit Finaled | 5/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 3/8/2024 | PATRICK LOPEZ |
| Permit | Cleared | 3/9/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/9/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2024 | CARLOS AGUILERA |
| ZI | Cleared | 3/12/2024 | ALEX VELA |
| Sewer availability | Cleared | 3/13/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/3/2024 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 9/11/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/11/2024 | Partial Inspection | MISAEL ESPARZA |
| Grounding or Bonding | 9/11/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/17/2024 | Approved | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 10/10/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 10/10/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/24/2024 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 10/24/2024 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 10/24/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/24/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/31/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 10/31/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 10/31/2024 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 10/31/2024 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 11/12/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/12/2024 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/3/2024 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/3/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 12/10/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/10/2024 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 12/18/2024 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 12/18/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/18/2024 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 3/6/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/6/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 3/6/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 3/6/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 3/6/2025 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 3/6/2025 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 3/11/2025 | Partial Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 3/14/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 3/14/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 3/14/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 4/11/2025 | Approved | MISAEL ESPARZA |
| Final | 4/11/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 4/11/2025 | Approved | MISAEL ESPARZA |
| Final | 5/1/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 5/1/2025 | Approved | MISAEL ESPARZA |