13944 W ADDISON ST 91423

Certificate Information: 13944 W ADDISON ST 91423

Application / Permit
24014-10000-00241
Plan Check / Job No.
B24LA00977
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* GROUND FLOOR ADDITION, ATTACHED 2-CAR GARAGE ADDITION, AND MAJOR REMODEL TO (E) 1-STORY SFD. NFPA 13D.
Permit Issued
Issued on 7/17/2024
Issuing Office
Current Status
CofO Issued on 5/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 VIVIAN LAO
Corrections Issued 2/9/2024 VIVIAN LAO
Quality Review Completed 2/9/2024 GARO TELMI
Applicant returned to address corrections 3/21/2024 VIVIAN LAO
Applicant returned to address corrections 4/3/2024 VIVIAN LAO
Plan Check Approved 4/19/2024 VIVIAN LAO
Issued 7/17/2024 APPLICANT
CofO in Progress 5/2/2025 MISAEL ESPARZA
Permit Finaled 5/12/2025 RUBEN SALAS
CofO Issued 5/12/2025 RUBEN SALAS
Permit Finaled 5/12/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 3/8/2024 PATRICK LOPEZ
Permit Cleared 3/9/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/9/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/12/2024 CARLOS AGUILERA
ZI Cleared 3/12/2024 ALEX VELA
Sewer availability Cleared 3/13/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/3/2024 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 9/11/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/11/2024 Partial Inspection MISAEL ESPARZA
Grounding or Bonding 9/11/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/17/2024 Approved MISAEL ESPARZA
Deputy Drilled-In Anchors 10/10/2024 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 10/10/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 10/24/2024 Corrections Issued MISAEL ESPARZA
Gas Test 10/24/2024 Partial Approval MISAEL ESPARZA
HVAC-Rough 10/24/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/24/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 10/31/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 10/31/2024 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 10/31/2024 Partial Approval MISAEL ESPARZA
Shower Pan 10/31/2024 Approved MISAEL ESPARZA
HVAC-Rough 11/12/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/12/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 12/3/2024 Approved MISAEL ESPARZA
Green Building Rough 12/3/2024 Not Ready for Inspection MISAEL ESPARZA
Insulation 12/10/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/10/2024 Partial Approval MISAEL ESPARZA
Drywall Nailing 12/18/2024 Approved MICHAEL CORTEZ
Green Building Rough 12/18/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 12/18/2024 Approved MICHAEL CORTEZ
ELECTRICAL-Final 3/6/2025 Corrections Issued MISAEL ESPARZA
Final 3/6/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 3/6/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 3/6/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 3/6/2025 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/6/2025 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 3/6/2025 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 3/11/2025 Partial Inspection MISAEL ESPARZA
ELECTRICAL-Final 3/14/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 3/14/2025 Approved MISAEL ESPARZA
PLUMBING-Final 3/14/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/11/2025 Approved MISAEL ESPARZA
Final 4/11/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 4/11/2025 Approved MISAEL ESPARZA
Final 5/1/2025 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 5/1/2025 Approved MISAEL ESPARZA