3980 S HEPBURN AVE 90008

Certificate Information: 3980 S HEPBURN AVE 90008

Application / Permit
24014-10000-00240
Plan Check / Job No.
B24LA00976
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
***ePlan*** Remodel of first floor ( convert interior space to new bedroom) and reduce of floor area of first floor and remodel bathroom on 2nd floor of (E) two story single family dwelling.
Permit Issued
Issued on 9/11/2024
Issuing Office
Current Status
Issued on 9/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/19/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 YASHAR EMAMI
Corrections Issued 1/29/2024 YASHAR EMAMI
Quality Review Completed 2/14/2024 REZA HAGHIGHAT
Applicant returned to address corrections 2/28/2024 YASHAR EMAMI
Applicant returned to address corrections 4/30/2024 YASHAR EMAMI
Applicant returned to address corrections 5/10/2024 YASHAR EMAMI
Applicant returned to address corrections 5/17/2024 YASHAR EMAMI
Applicant returned to address corrections 8/8/2024 YASHAR EMAMI
Applicant returned to address corrections 8/16/2024 YASHAR EMAMI
Plan Check Approved 9/10/2024 YASHAR EMAMI
Issued 9/11/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/28/2024 JUSTIN BICOL
Sewer availability Cleared 2/28/2024 JUSTIN BICOL
Low Impact Development (LID) Cleared 7/15/2024 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 8/7/2024 TREVOR QUAN
Hold Cleared 4/23/2025 MARIA VENDIVIL
Hold Cleared 7/30/2025 ALEXIS SCHULTZ

Contact Information

Contractor Owner-Builder       ,
Engineer Bayoumi,, Mostafa H; Lic. No.: C94270 250 WEST GOBBI ST LOT 6      UKIAH, CA 95482

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/25/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Partial Approval LUIS CASTRO
Insulation 5/12/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 8/4/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 8/4/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 8/4/2025 Approved LUIS CASTRO
Green Building Rough 8/4/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 8/4/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 8/4/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 8/5/2025 Corrections Issued LUIS CASTRO
HVAC-Rough 8/5/2025 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 8/13/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 8/13/2025 Approved LUIS CASTRO
Green Building Rough 8/13/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 8/13/2025 Partial Approval LUIS CASTRO
Deputy Steel/Welding 8/19/2025 Conditional Approval LUIS CASTRO
Insulation 8/19/2025 Corrections Issued RONNIE MEDINA
Shower Pan 8/19/2025 Approved RONNIE MEDINA
HVAC-Rough 8/22/2025 Approved ANTHONY RAMOS
Insulation 8/22/2025 Approved ANTHONY RAMOS
Drywall Nailing 8/28/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 9/12/2025 Approved LUIS CASTRO
Final 4/6/2026 Corrections Issued LUIS CASTRO
Green Building Final 4/6/2026 Not Ready for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 4/6/2026 SGSOV Approved LUIS CASTRO
Smoke Detectors 4/6/2026 Approved LUIS CASTRO