2718 W 70TH ST 90043
Certificate Information: 2718 W 70TH ST 90043
- Application / Permit
- 24014-10000-00214
- Plan Check / Job No.
- B24LA00876
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH ADDITION INTO A (N) ACCESSORY DWELLING UNIT AND PORCH PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- Current Status
- CofO Issued on 1/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 1/20/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 6/20/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 7/11/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 7/17/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 7/29/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 8/2/2024 | ALEC MOUSAKHANIAN |
| Issued | 2/4/2025 | APPLICANT |
| CofO in Progress | 1/16/2026 | SALVADOR MARTINEZ |
| Permit Finaled | 1/16/2026 | DEROLD HAUFF |
| CofO Issued | 1/16/2026 | DEROLD HAUFF |
| Permit Finaled | 1/16/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | JEANIE LAM |
| Sewer availability | Cleared | 1/29/2024 | JEANIE LAM |
| Address approval | Cleared | 1/30/2024 | JEANIE LAM |
| Construction near power lines | Cleared | 5/20/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 5/20/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 6/17/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/9/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/24/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 5/1/2025 | Approved | WAYNE REGESTER |
| Gas Test | 7/9/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 7/9/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 8/14/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 8/14/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 8/21/2025 | Approved | ANTHONY RAMOS |
| HVAC-Rough | 8/21/2025 | Partial Approval | ANTHONY RAMOS |
| PLUMBING-Rough | 8/21/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 8/26/2025 | Corrections Issued | RONNIE MEDINA |
| Drywall Nailing | 9/9/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 9/9/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 9/9/2025 | Partial Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 11/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 11/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 11/5/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 11/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 11/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 11/5/2025 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Final | 12/10/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 12/19/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Final | 12/24/2025 | No Access for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/24/2025 | SGSOV Not Ready | SABAS ALONSO |
| Final | 12/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 1/13/2026 | OK to Issue CofO | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Approved | SALVADOR MARTINEZ |