2718 W 70TH ST 90043

Certificate Information: 2718 W 70TH ST 90043

Application / Permit
24014-10000-00214
Plan Check / Job No.
B24LA00876
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH ADDITION INTO A (N) ACCESSORY DWELLING UNIT AND PORCH PER LAMC 12.22 A.33(c)-(d).
Permit Issued
Issued on 2/4/2025
Issuing Office
Current Status
CofO Issued on 1/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2024 APPLICANT
Assigned to Plan Check Engineer 1/19/2024 GIOVANNY CHAVEZ
Corrections Issued 1/20/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 6/20/2024 GURUNATH NESARAJAH
Applicant returned to address corrections 7/11/2024 GURUNATH NESARAJAH
Applicant returned to address corrections 7/17/2024 GURUNATH NESARAJAH
Applicant returned to address corrections 7/29/2024 GIOVANNY CHAVEZ
Plan Check Approved 8/2/2024 ALEC MOUSAKHANIAN
Issued 2/4/2025 APPLICANT
CofO in Progress 1/16/2026 SALVADOR MARTINEZ
Permit Finaled 1/16/2026 DEROLD HAUFF
CofO Issued 1/16/2026 DEROLD HAUFF
Permit Finaled 1/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/29/2024 JEANIE LAM
Sewer availability Cleared 1/29/2024 JEANIE LAM
Address approval Cleared 1/30/2024 JEANIE LAM
Construction near power lines Cleared 5/20/2024 RIDWAN HARDY
Construction within easement Cleared 5/20/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 6/17/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/9/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/24/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 5/1/2025 Approved WAYNE REGESTER
Gas Test 7/9/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 7/9/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 8/14/2025 Approved WAYNE REGESTER
Green Building Rough 8/14/2025 Approved WAYNE REGESTER
Drywall Nailing 8/21/2025 Approved ANTHONY RAMOS
HVAC-Rough 8/21/2025 Partial Approval ANTHONY RAMOS
PLUMBING-Rough 8/21/2025 Approved ANTHONY RAMOS
Drywall Nailing 8/26/2025 Corrections Issued RONNIE MEDINA
Drywall Nailing 9/9/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 9/9/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 9/9/2025 Partial Inspection SALVADOR MARTINEZ
ELECTRICAL-Final 11/5/2025 Corrections Issued SALVADOR MARTINEZ
Final 11/5/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 11/5/2025 Approved SALVADOR MARTINEZ
HVAC-Final 11/5/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 11/5/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 11/5/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 12/8/2025 SGSOV Not Ready SALVADOR MARTINEZ
Final 12/10/2025 Corrections Issued SALVADOR MARTINEZ
Final 12/19/2025 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Not Ready SALVADOR MARTINEZ
Final 12/24/2025 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Not Ready SABAS ALONSO
Final 12/29/2025 Corrections Issued SALVADOR MARTINEZ
Final 1/13/2026 OK to Issue CofO SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved SALVADOR MARTINEZ