937 E 106TH ST 90002
Certificate Information: 937 E 106TH ST 90002
- Application / Permit
- 24014-10000-00196
- Plan Check / Job No.
- B24LA00818
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 2-CAR CARPORT TO ADU, GROUND AND 2ND STORY ADDITION TO ADU PER LAMC 12.22A.33(c)-(d)
- Permit Issued
- Issued on 1/28/2025
- Issuing Office
- Current Status
- Issued on 1/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | VIVIAN LAO |
| Corrections Issued | 2/7/2024 | VIVIAN LAO |
| Quality Review Completed | 2/9/2024 | KEN GILL |
| Applicant returned to address corrections | 9/20/2024 | VIVIAN LAO |
| Plan Check Approved | 1/24/2025 | VIVIAN LAO |
| Issued | 1/28/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2024 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 8/24/2024 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/3/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 9/5/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/22/2025 | Partial Approval | ANTHONY EGSON |
| Sewer | 4/30/2025 | Corrections Issued | ANTHONY EGSON |
| Sewer | 5/1/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 5/9/2025 | Corrections Issued | ANTHONY EGSON |
| Sewer | 5/14/2025 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 5/22/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/22/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/27/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/14/2025 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 12/15/2025 | Approved | ARTHUR NEGRETE |
| Pre-Inspection | 3/7/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Pre-Inspection | 3/7/2026 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 3/31/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 3/31/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 3/31/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 3/31/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 3/31/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 3/31/2026 | Approved | ARTHUR NEGRETE |
| Sewer | 3/31/2026 | Approved | ARTHUR NEGRETE |
| Insulation | 4/13/2026 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 4/21/2026 | Approved | ARTHUR NEGRETE |
| Shower Pan | 5/15/2026 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 5/19/2026 | Approved | ARTHUR NEGRETE |