2415 N DITMAN AVE 90032
Certificate Information: 2415 N DITMAN AVE 90032
- Application / Permit
- 24014-10000-00171
- Plan Check / Job No.
- B24LA00707
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING WITH INTERIOR REMODEL. ADD NEW WINDOWS AND DOORS PER PLAN. WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 7/22/2024
- Issuing Office
- Current Status
- CofO Issued on 1/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | SERGIO MUNIZ |
| Corrections Issued | 1/22/2024 | SERGIO MUNIZ |
| Plan Check Approved | 7/19/2024 | JEROME MAGAT PALMA |
| Issued | 7/22/2024 | APPLICANT |
| CofO in Progress | 1/2/2025 | BRENDAN MORELLI |
| Permit Finaled | 1/3/2025 | DEROLD HAUFF |
| CofO Issued | 1/3/2025 | DEROLD HAUFF |
| Permit Finaled | 1/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 2/3/2024 | CELINA MORENO |
| Sewer availability | Cleared | 2/3/2024 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 2/7/2024 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2024 | CELINA MORENO |
| Disturb/Remove Protected Trees | Cleared | 3/18/2024 | ADALBERTO VERA |
| "Q" conditions | Cleared | 6/12/2024 | DALIA MOKAYED |
| ZI | Cleared | 6/12/2024 | DALIA MOKAYED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/24/2024 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/24/2024 | Conditional Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/29/2024 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 7/29/2024 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Rough | 7/29/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Wood Frame | 7/29/2024 | Partial Approval | BRENDAN MORELLI |
| HVAC-Rough | 8/19/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/3/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/3/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 9/3/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 9/3/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/4/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 9/4/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Deputy Wood Construction | 9/9/2024 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/10/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 9/10/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 9/10/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/16/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 10/16/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 10/16/2024 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 10/17/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/18/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 10/18/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/18/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/18/2024 | Partial Approval | LILIANA PORTILLO |
| Insulation | 10/22/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/22/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/29/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 12/26/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 12/26/2024 | Approved | LILIANA PORTILLO |
| Green Building Final | 12/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 12/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 12/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 12/26/2024 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 12/26/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/27/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/27/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 12/27/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/30/2024 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 12/30/2024 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 12/30/2024 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 12/31/2024 | Approved | BRENDAN MORELLI |
| Final | 12/31/2024 | OK to Issue CofO | BRENDAN MORELLI |
| Green Building Final | 12/31/2024 | Approved | BRENDAN MORELLI |