13240 W LAKE ST 90066
Certificate Information: 13240 W LAKE ST 90066
- Application / Permit
- 24014-10000-00170
- Plan Check / Job No.
- B24LA00698
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *eplan* Second floor addition to (E) SFD. Remodel (E) SFD and enclose (E) first floor porch
- Permit Issued
- Issued on 4/29/2024
- Issuing Office
- Current Status
- CofO Issued on 7/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | WEIJIAN HUANG |
| Corrections Issued | 2/5/2024 | WEIJIAN HUANG |
| Quality Review Completed | 2/15/2024 | DANIEL CHAN |
| Plan Check Approved | 4/23/2024 | WEIJIAN HUANG |
| Issued | 4/29/2024 | APPLICANT |
| CofO in Progress | 7/18/2025 | DAVID FEILER |
| Permit Finaled | 7/26/2025 | RICHARD STEINBACH |
| CofO Issued | 7/26/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/26/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2024 | DARIN LAM |
| Sewer availability | Cleared | 2/21/2024 | DARIN LAM |
| Specific Plan | Cleared | 2/28/2024 | FREDDY GARCIA |
| Low Impact Development (LID) | Cleared | 3/25/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 4/3/2024 | DARIN LAM |
| GPI Written Notices | Cleared | 4/22/2024 | ROBERT PINA |
| Grading Pre-Inspection | Cleared | 4/22/2024 | ROBERT PINA |
Contact Information
| Architect | Fallen,, Keith; Lic. No.: NA34528 | , |
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Clark Kitchen Cabinets; Lic. No.: 645164-B | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/10/2024 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/10/2024 | Approved | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 6/18/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 8/22/2024 | Conditional Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/17/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/18/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 9/20/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Partial Approval | JESUS PINEDA |
| Deputy Wood Construction | 10/9/2024 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 10/21/2024 | Corrections Issued | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 10/21/2024 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 10/22/2024 | Conditional Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 10/29/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 10/29/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 10/29/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/30/2024 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/31/2024 | Approved | JESUS PINEDA |
| Insulation | 10/31/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/31/2024 | Partial Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 11/7/2024 | Approved | JESUS PINEDA |
| Shower Pan | 11/7/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 11/14/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 3/5/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 3/5/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 3/5/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 3/7/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 3/7/2025 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 3/7/2025 | Approved | JESUS PINEDA |
| Final | 3/10/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 3/10/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2025 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 3/10/2025 | Approved | ARAM AVEDISIAN |
| Final | 7/18/2025 | OK to Issue CofO | DAVID FEILER |