7907 S CROYDON AVE 90045

Certificate Information: 7907 S CROYDON AVE 90045

Application / Permit
24014-10000-00165
Plan Check / Job No.
B24LA00657
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION(31'-1" x 15'-9") FOR A MASTER BED AND BATH AT REAR WITH INTERIOR REMODEL TO EXISTING SINGLE FAMILY DWELLING .
Permit Issued
Issued on 8/25/2024
Issuing Office
Current Status
CofO Issued on 6/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2024 APPLICANT
Assigned to Plan Check Engineer 1/17/2024 DANIEL ABRAMYAN
Corrections Issued 1/18/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 4/1/2024 SERGIO MUNIZ
Plan Check Approved 8/23/2024 SAMUEL GONZALEZ
Issued 8/25/2024 APPLICANT
CofO in Progress 6/23/2025 ARAM AVEDISIAN
Permit Finaled 6/26/2025 RICHARD STEINBACH
CofO Issued 6/26/2025 RICHARD STEINBACH
Permit Finaled 6/26/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/8/2024 KIMBERLY HERNANDEZ
Specific Plan Cleared 8/8/2024 JOSHUA JONES
Low Impact Development (LID) Cleared 8/20/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 8/21/2024 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Shirley,, Peter; Lic. No.: NA75050       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/28/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 9/6/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 11/26/2024 Partial Approval MICHAEL ALLEN
ELECTRICAL-Rough 12/11/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 12/11/2024 Approved HERBERT GIRON
PLUMBING-Rough 12/11/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 12/13/2024 Conditional Approval TEMISTOCLES CAAL
PLUMBING-Rough 12/13/2024 Approved TEMISTOCLES CAAL
Special/Order Compliance 12/13/2024 Partial Inspection JAYLIN GRAVITTE
Wood Frame 12/13/2024 Approved TEMISTOCLES CAAL
Insulation 12/26/2024 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Rough 12/31/2024 Approved TEMISTOCLES CAAL
Insulation 12/31/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 1/14/2025 Approved JAYLIN GRAVITTE
Special/Order Compliance 1/14/2025 Partial Inspection BOBBY KEY
Shower Pan 1/30/2025 Approved TEMISTOCLES CAAL
Gas Test 1/31/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 2/10/2025 Approved TEMISTOCLES CAAL
Green Building Final 4/30/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 4/30/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 4/30/2025 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 4/30/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 5/2/2025 Approved TEMISTOCLES CAAL
Final 5/2/2025 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 5/5/2025 Approved JESUS PINEDA
ELECTRICAL-Final 5/5/2025 Not Ready for Inspection JESUS PINEDA
Final 5/5/2025 Corrections Issued JESUS PINEDA
Service/Power Release 5/5/2025 Approved JESUS PINEDA
Special/Order Compliance 5/5/2025 Partial Inspection JAYLIN GRAVITTE
Final 6/23/2025 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 6/23/2025 Approved ARAM AVEDISIAN