10818 N LOUISE AVE 91344

Certificate Information: 10818 N LOUISE AVE 91344

Application / Permit
24014-10000-00162
Plan Check / Job No.
B23VN17021
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
***EPLAN*** PROPOSED DETACHED 1-STORY ACCESSORY DWELLING UNIT PER ORDINANCE. ***SHALL BE SPRINKLERED PER NFPA 13D*** 2 OF 2
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
CofO Issued on 2/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 MICHAEL LOPEZ
Corrections Issued 1/24/2024 MICHAEL LOPEZ
Quality Review Completed 1/24/2024 PRANITA SHAH
Applicant returned to address corrections 3/20/2024 MICHAEL LOPEZ
Applicant returned to address corrections 4/23/2024 TSE MING HUANG
Applicant returned to address corrections 6/24/2024 MICHAEL LOPEZ
Applicant returned to address corrections 9/30/2024 MICHAEL LOPEZ
Plan Check Approved 1/30/2025 MICHAEL LOPEZ
Issued 3/12/2025 APPLICANT
CofO in Progress 1/20/2026 STEVEN BACK
Permit Finaled 2/5/2026 JOHN JANSON
CofO Issued 2/5/2026 JOHN JANSON
Permit Finaled 2/5/2026 JOHN JANSON

Permit Application Clearance Information

CPC Cleared 3/20/2024 ASHLEY RODARTE
CPC Cleared 3/20/2024 ASHLEY RODARTE
Address approval Cleared 3/21/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 6/13/2024 CARLOS RAMIREZ
Sewer availability Cleared 6/13/2024 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 9/18/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 1/13/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mniarji,, Majd Sameer; Lic. No.: C93049 7812 VASSAR AVENUE      CANOGA PARK, CA 91304

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/30/2025 Partial Approval STEVEN BACK
Pre-Inspection 4/30/2025 Partial Inspection STEVEN BACK
Excavation/Setback/Form/Re-Bar 5/27/2025 Approved STEVEN BACK
Footing/Foundation/Slab 5/27/2025 Approved STEVEN BACK
ELECTRICAL-Rough 7/10/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Approved STEVEN BACK
Pre-Inspection 7/10/2025 Corrections Issued STEVEN BACK
Final 7/25/2025 Corrections Issued STEVEN BACK
HVAC-Rough 7/25/2025 Approved STEVEN BACK
HVAC-Rough 7/31/2025 Approved STEVEN BACK
PLUMBING-Rough 7/31/2025 Approved STEVEN BACK
Shower Pan 8/27/2025 Approved STEVEN BACK
BUILDING-Rough-Frame 9/3/2025 Approved STEVEN BACK
Green Building Rough 9/3/2025 Approved STEVEN BACK
Insulation 9/3/2025 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 9/3/2025 Approved STEVEN BACK
Verify Sprinkler Sign Off 9/3/2025 Approved STEVEN BACK
Insulation 9/15/2025 Corrections Issued CHRIS CHRISTENSEN
Insulation 9/17/2025 Approved SCOTT SOBEL
Drywall Nailing 9/25/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 11/3/2025 Corrections Issued STEVEN BACK
HVAC-Final 11/14/2025 Approved KRISTEN CAUSEY
PLUMBING-Final 11/14/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Final 12/4/2025 Not Ready for Inspection DAVID SCANTLIN
Final 1/14/2026 Corrections Issued STEVEN BACK
Green Building Final 1/14/2026 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 1/14/2026 SGSOV Not Required STEVEN BACK
Service/Power Release 1/14/2026 Not Ready for Inspection STEVEN BACK
Smoke Detectors 1/14/2026 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Final 1/20/2026 Approved STEVEN BACK
Final 1/20/2026 OK to Issue CofO STEVEN BACK
Service/Power Release 1/20/2026 Approved STEVEN BACK
Smoke Detectors 1/20/2026 Approved STEVEN BACK