3845 S CARMONA AVE 90008
Certificate Information: 3845 S CARMONA AVE 90008
- Application / Permit
- 24014-10000-00146
- Plan Check / Job No.
- B24LA00602
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and exterior alteration to existing 2-story single family dwelling with attached garage. Work per WFPP.
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2024 | VICTOR CHEN |
| Corrections Issued | 1/19/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 3/19/2024 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 3/25/2024 | ZAW HAN |
| Plan Check Approved | 4/2/2024 | KHUONG TRUONG |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 12/24/2024 | LUIS CASTRO |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
| CofO Issued | 1/9/2025 | DEROLD HAUFF |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/23/2024 | CHARLES POWELL |
| Miscellaneous | Cleared | 3/20/2024 | VICTOR CHEN |
| Roof/Waste drainage to street | Cleared | 3/27/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2024 | JESSICA OPINION |
Contact Information
| Contractor | Pure Passion Builders Inc; Lic. No.: 1102664-B | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/23/2024 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/24/2024 | Corrections Issued | ANTHONY EGSON |
| METHANE-Barrier | 7/24/2024 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Subgrade | 7/24/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Pre-Inspection | 7/29/2024 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/5/2024 | Partial Inspection | ANTHONY EGSON |
| Green Building Rough | 8/5/2024 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Rough | 8/5/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/9/2024 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 8/9/2024 | Approved | ANTHONY EGSON |
| Insulation | 8/13/2024 | Partial Approval | ALEX COLIN |
| Interior/Exterior Lathing | 8/14/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/30/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 8/30/2024 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Rough | 8/30/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 8/30/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/4/2024 | Approved | ANTHONY EGSON |
| Insulation | 9/9/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 9/11/2024 | Approved | ANTHONY EGSON |
| Final | 12/3/2024 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 12/3/2024 | Approved | BARRY HACHE |
| METHANE-Barrier | 12/3/2024 | Approved | BARRY HACHE |
| METHANE-Subgrade | 12/3/2024 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 12/19/2024 | Approved | LUIS CASTRO |
| Final | 12/19/2024 | Conditional Approval | LUIS CASTRO |
| Green Building Final | 12/19/2024 | Approved | LUIS CASTRO |
| Green Building Rough | 12/19/2024 | Approved | LUIS CASTRO |
| METHANE-Final | 12/19/2024 | Approved | LUIS CASTRO |
| METHANE-Rough | 12/19/2024 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 12/19/2024 | Approved | LUIS CASTRO |
| Final | 12/24/2024 | OK to Issue CofO | LUIS CASTRO |