- ePlan Two story addition to (e) one story SFD and interior remodel. To be fully sprinklered NFPA 13D
- Permit Issued
- Issued on 5/28/2024
- Issuing Office
- Current Status
- CofO Issued on 4/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 2/3/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 2/6/2024 | GARO TELMI |
| Applicant returned to address corrections | 4/8/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 5/3/2024 | MARCELA FRANQUEZ |
| Issued | 5/28/2024 | APPLICANT |
| CofO in Progress | 4/28/2025 | BRENDAN MORELLI |
| Permit Finaled | 4/30/2025 | DEROLD HAUFF |
| CofO Issued | 4/30/2025 | DEROLD HAUFF |
| Permit Finaled | 4/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/8/2024 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 4/12/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/16/2024 | DAVID LOPEZ |
Contact Information
| Architect | Baek,, Sunpil; Lic. No.: C35323 | 4041 WILSHIRE BLVD #103 LOS ANGELES, CA 90010 |
| Architect | Baek,, Sunpil; Lic. No.: NA35323 | , |
| Contractor | Good Tree Construction Inc; Lic. No.: 1013101-B | , |
| Engineer | Hwang,, Junho; Lic. No.: NA5592 | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/20/2024 | No Access for Inspection | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/26/2024 | Approved | RICHARD DOCKUS |
| METHANE-Barrier | 6/26/2024 | Approved | RICHARD DOCKUS |
| METHANE-Subgrade | 6/26/2024 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 8/29/2024 | Approved | JEFFREY MEAD |
| Gas Test | 8/29/2024 | Approved | JEFFREY MEAD |
| METHANE-Rough | 8/29/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 8/29/2024 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/4/2024 | Corrections Issued | JOSE MACIAS |
| Gas Test | 9/4/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 9/4/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 9/4/2024 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 9/6/2024 | Not Ready for Inspection | LUIS CASTRO |
| Deputy Wood Construction | 9/6/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Partial Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 9/6/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 9/10/2024 | Corrections Issued | JOSE MACIAS |
| Deputy Wood Construction | 9/10/2024 | Conditional Approval | JOSE MACIAS |
| Insulation | 9/10/2024 | Corrections Issued | JOSE MACIAS |
| Insulation | 9/12/2024 | Corrections Issued | JEFFREY MEAD |
| Deputy Wood Construction | 9/16/2024 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/17/2024 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Approved | JEFFREY MEAD |
| Insulation | 9/17/2024 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 9/18/2024 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/26/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 9/26/2024 | Partial Approval | JEFFREY MEAD |
| Shower Pan | 9/26/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Drywall Nailing | 9/30/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 9/30/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Shower Pan | 9/30/2024 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 11/26/2024 | Approved | JEFFREY MEAD |
| Final | 1/6/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/6/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 1/6/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/6/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 2/6/2025 | Conditional Approval | JEFFREY MEAD |
| PLUMBING-Final | 2/6/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 2/25/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 2/25/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 2/25/2025 | Approved | JEFFREY MEAD |
| Service/Power Release | 2/25/2025 | Not Required | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Not Ready | JEFFREY MEAD |
| Final | 4/15/2025 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 4/15/2025 | Approved | JEFFREY MEAD |
| Final | 4/22/2025 | Corrections Issued | JOSE MACIAS |
| Final | 4/28/2025 | OK to Issue CofO | BRENDAN MORELLI |