2517-2519 S TILDEN AVE 90064

Certificate Information: 2517-2519 S TILDEN AVE 90064

Application / Permit
24014-10000-00089
Plan Check / Job No.
B24LA00316
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO A (N) 384 SF ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/18/2024
Issuing Office
Current Status
CofO Issued on 11/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 LUISANGEL VALENZUELA
Corrections Issued 1/12/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/15/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/6/2024 ALEC MOUSAKHANIAN
Plan Check Approved 3/7/2024 ALEC MOUSAKHANIAN
No Progress 3/18/2024 LUISANGEL VALENZUELA
Plan Check Approved 3/18/2024 LUISANGEL VALENZUELA
Issued 3/18/2024 APPLICANT
CofO in Progress 11/2/2024 MICHAEL PELHAM
Permit Finaled 11/19/2024 RICHARD STEINBACH
CofO Issued 11/19/2024 RICHARD STEINBACH
Permit Finaled 11/19/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/18/2024 DARIN LAM
Sewer availability Cleared 1/18/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 1/19/2024 DARIN LAM
Specific Plan Cleared 2/7/2024 PEDRO AYALA
Grading Pre-Inspection Cleared 2/14/2024 VASIL MIHALEV

Contact Information

Contractor The Adu Guys Com Inc; Lic. No.: 1071442-B       ,
Contractor The Adu Guys.Com Inc; Lic. No.: 1071442-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/21/2024 Partial Approval JESUS PINEDA
Sewer 3/21/2024 Approved JESUS PINEDA
Deputy Drilled-In Anchors 3/22/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 3/28/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 4/12/2024 Corrections Issued TEMISTOCLES CAAL
Deputy Drilled-In Anchors 4/23/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 4/25/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 5/8/2024 Approved ASHLEY THOMPSON
HVAC-Rough 5/8/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 5/8/2024 Corrections Issued ASHLEY THOMPSON
Rough-Elec/Plmb/HVAC 5/8/2024 Not Ready for Inspection ASHLEY THOMPSON
Rough-Elec/Plmb/HVAC 5/13/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/31/2024 Partial Approval JESUS PINEDA
Green Building Rough 5/31/2024 Approved JESUS PINEDA
Insulation 5/31/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 5/31/2024 Partial Approval JESUS PINEDA
Drywall Nailing 6/7/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 8/29/2024 Approved ARAM AVEDISIAN
Final 8/29/2024 Corrections Issued ARAM AVEDISIAN
Green Building Final 8/29/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/29/2024 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 8/29/2024 Approved ARAM AVEDISIAN
Final 9/5/2024 Partial Approval DANIEL VERA
Final 9/14/2024 Corrections Issued MICHAEL PELHAM
Final 11/1/2024 OK to Issue CofO MICHAEL PELHAM