11277-11279 W CHARNOCK ROAD 90066

Certificate Information: 11277-11279 W CHARNOCK ROAD 90066

Application / Permit
24014-10000-00079
Plan Check / Job No.
B23LA24699
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: New 583 SF 1 story addition to existing single-family home for new attached ADU per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 4/22/2024
Issuing Office
Current Status
CofO Issued on 5/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2024 APPLICANT
Assigned to Plan Check Engineer 1/10/2024 AMY GUEVARRA
Corrections Issued 1/17/2024 AMY GUEVARRA
Applicant returned to address corrections 2/17/2024 AMY GUEVARRA
Plan Check Approved 3/7/2024 AMY GUEVARRA
Issued 4/22/2024 APPLICANT
CofO in Progress 5/20/2025 WILBER ROSALES
Permit Finaled 5/20/2025 RICHARD STEINBACH
CofO Issued 5/20/2025 RICHARD STEINBACH
Permit Finaled 5/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/23/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 1/24/2024 DARIN LAM
Sewer availability Cleared 1/24/2024 DARIN LAM
Specific Plan Cleared 2/14/2024 PEDRO AYALA
Grading Pre-Inspection Cleared 2/16/2024 MICHAEL TEMPLE
Low Impact Development (LID) Cleared 3/4/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 3/5/2024 DARIN LAM

Contact Information

Contractor Copper Construction Llc; Lic. No.: 1060557-B       ,
Engineer Chen,, Junfei; Lic. No.: C85841 50 OUTLAW      IRVINE, CA 92602

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/7/2024 Partial Approval JESUS PINEDA
Sewer 6/7/2024 Approved JESUS PINEDA
Underground Mechanical 6/7/2024 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 6/18/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Approved JESUS PINEDA
Underground Mechanical 7/15/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 10/18/2024 Partial Approval DANIEL VERA
HVAC-Rough 10/18/2024 Approved DANIEL VERA
PLUMBING-Rough 10/18/2024 Not Ready for Inspection DANIEL VERA
Wood Frame 10/18/2024 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 10/22/2024 Approved DANIEL VERA
PLUMBING-Rough 10/22/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 10/28/2024 Approved DANIEL VERA
ELECTRICAL-Rough 10/28/2024 Corrections Issued DANIEL VERA
Interior/Exterior Lathing 10/28/2024 Partial Approval DANIEL VERA
MERV13>=Rough 10/28/2024 Approved DANIEL VERA
Insulation 11/5/2024 Approved DANIEL VERA
Interior/Exterior Lathing 11/5/2024 Not Ready for Inspection DANIEL VERA
Shower Pan 11/5/2024 Approved DANIEL VERA
Interior/Exterior Lathing 11/13/2024 Approved REGINA MENDEZ
Drywall Nailing 12/6/2024 Approved BOBBY KEY
ELECTRICAL-Rough 12/6/2024 Approved BOBBY KEY
Footing/Foundation/Slab 12/6/2024 Approved BOBBY KEY
ELECTRICAL-Final 5/14/2025 Approved WILBER ROSALES
Final 5/14/2025 Corrections Issued WILBER ROSALES
HVAC-Final 5/14/2025 Approved WILBER ROSALES
MERV13>=Final 5/14/2025 Approved WILBER ROSALES
PLUMBING-Final 5/14/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 5/14/2025 Approved WILBER ROSALES
Final 5/19/2025 OK to Issue CofO WILBER ROSALES