2115 S BUCKINGHAM ROAD 90016

Certificate Information: 2115 S BUCKINGHAM ROAD 90016

Application / Permit
24014-10000-00075
Plan Check / Job No.
B24LA00275
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN***PROPOSED 2-STORY ADDITION AND REMODEL TO SINGLE FAMILY DWELLING
Permit Issued
Issued on 3/25/2024
Issuing Office
Current Status
Issued on 3/25/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/10/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 SINA KHOSRAVI
Corrections Issued 1/24/2024 SINA KHOSRAVI
Quality Review Completed 2/7/2024 GARO TELMI
Plan Check Approved 3/21/2024 SINA KHOSRAVI
Issued 3/25/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/8/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 3/8/2024 TREVOR QUAN
Sewer availability Cleared 3/8/2024 TREVOR QUAN

Contact Information

Architect Becker,, Kelly; Lic. No.: C36255       ,
Contractor Owner-Builder       ,
Engineer Kile,, Johnny C; Lic. No.: C92658 2514 W OXFORD STREET      PHILADELPHIA, PA 19121

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/14/2024 Approved JUSTIN HAWLEY
Footing/Foundation/Slab 7/3/2024 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/11/2024 No Access for Inspection JUSTIN HAWLEY
PLUMBING-Rough 7/11/2024 No Access for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 7/12/2024 Partial Approval JUSTIN HAWLEY
PLUMBING-Rough 7/12/2024 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 7/15/2024 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Partial Approval JUSTIN HAWLEY
Pre-Inspection 8/21/2024 Approved JUSTIN HAWLEY
Footing/Foundation/Slab 9/3/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 10/28/2024 Approved JOSE MACIAS
Deputy Wood Construction 10/29/2024 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 11/5/2024 Partial Approval JUSTIN HAWLEY
HVAC-Rough 11/5/2024 Approved JUSTIN HAWLEY
MERV13>=Rough 11/5/2024 Approved JUSTIN HAWLEY
Insulation 11/13/2024 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 11/19/2024 Approved JOHN QUINTANILLA
Drywall Nailing 11/22/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 3/26/2025 No Access for Inspection JOSE MACIAS
Final 3/26/2025 No Access for Inspection JOSE MACIAS
MERV13>=Final 3/26/2025 No Access for Inspection JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 3/26/2025 SGSOV Not Ready JOSE MACIAS
Smoke Detectors 3/26/2025 No Access for Inspection JOSE MACIAS
BUILDING-Rough-Frame 3/27/2025 Approved JOSE MACIAS
Final 3/27/2025 Corrections Issued JOSE MACIAS
MERV13>=Final 3/27/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Approved JOSE MACIAS
Smoke Detectors 3/27/2025 Approved JOSE MACIAS
Wood Frame 3/27/2025 Approved JOSE MACIAS
PLUMBING-Final 3/28/2025 No Access for Inspection ENRIQUE MIRELES