8102 S CREIGHTON AVE 90045

Certificate Information: 8102 S CREIGHTON AVE 90045

Application / Permit
24014-10000-00068
Plan Check / Job No.
B24LA00265
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert Existing Garage into ADU + Addition
Permit Issued
Issued on 3/25/2024
Issuing Office
Current Status
CofO Issued on 10/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2024 APPLICANT
Assigned to Plan Check Engineer 1/19/2024 EDWIN ESPIN
Corrections Issued 1/22/2024 EDWIN ESPIN
Plan Check Approved 3/20/2024 EDWIN ESPIN
Issued 3/25/2024 APPLICANT
CofO in Progress 10/25/2024 BOBBY KEY
CofO Issued 10/30/2024 RICHARD STEINBACH
Permit Finaled 10/30/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/24/2024 DARIN LAM
Roof/Waste drainage to street Cleared 1/24/2024 DARIN LAM
Specific Plan Cleared 1/25/2024 ALESSANDRO MERCURI
Eng Process Fee Ord 176,300 Cleared 3/4/2024 DARIN LAM
Sewer availability Cleared 3/4/2024 DARIN LAM

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: NA21514       ,
Contractor H A S Construction Inc; Lic. No.: 538538-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/17/2024 Partial Approval HERBERT GIRON
Underground Mechanical 4/17/2024 Partial Approval HERBERT GIRON
Deputy Drilled-In Anchors 4/23/2024 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 4/25/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/3/2024 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 6/13/2024 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 6/13/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Corrections Issued BOBBY KEY
Green Building Rough 6/13/2024 Not Ready for Inspection BOBBY KEY
HVAC-Rough 6/13/2024 Approved BOBBY KEY
PLUMBING-Rough 6/13/2024 Approved BOBBY KEY
Deputy Wood Construction 6/14/2024 Conditional Approval RICHARD STEINBACH
Interior/Exterior Lathing 7/8/2024 Partial Approval RICHARD STEINBACH
BUILDING-Rough-Frame 7/15/2024 Corrections Issued BOBBY KEY
Green Building Rough 7/15/2024 Approved BOBBY KEY
Insulation 7/15/2024 Not Ready for Inspection BOBBY KEY
Shower Pan 7/15/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 7/23/2024 Approved BOBBY KEY
Insulation 7/23/2024 Approved BOBBY KEY
Drywall Nailing 7/26/2024 Approved BOBBY KEY
Interior/Exterior Lathing 8/2/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 10/16/2024 Corrections Issued BOBBY KEY
Final 10/16/2024 Corrections Issued BOBBY KEY
Green Building Final 10/16/2024 Approved BOBBY KEY
HVAC-Final 10/16/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 10/16/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 10/16/2024 Approved BOBBY KEY
ELECTRICAL-Final 10/25/2024 Approved BOBBY KEY
Final 10/25/2024 OK to Issue CofO BOBBY KEY
HVAC-Final 10/25/2024 Approved BOBBY KEY
PLUMBING-Final 10/25/2024 Approved BOBBY KEY