5232 N WINDERMERE AVE 90041
Certificate Information: 5232 N WINDERMERE AVE 90041
- Application / Permit
- 24014-10000-00060
- Plan Check / Job No.
- B23LA24685
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 197 SF PORTION OF THE (E) SFD AND CONTRUCT NEW 32'3" X 33'4" IRREGULAR SHAPED ADDITION TO THE REAR OF THE (E) SFD INCLUDING ATTACHED PATIO COVER. WORK PER ENGINEERING. NFPA FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- Current Status
- Issued on 9/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2024 | OMAR GARNICA |
| Corrections Issued | 1/11/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 2/22/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 3/15/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 6/11/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 8/29/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 9/12/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 9/20/2024 | ALEC MOUSAKHANIAN |
| Issued | 9/30/2024 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/21/2024 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2024 | ARNULFO CHAMU |
| Grading Pre-Inspection | Cleared | 3/6/2024 | MICHAEL TEMPLE |
| Low Impact Development (LID) | Cleared | 6/6/2024 | MARCO SANCHEZ |
| GPI Written Notices | Cleared | 6/11/2024 | OMAR GARNICA |
| Roof/Waste drainage to street | Cleared | 8/26/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/19/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 3/19/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Partial Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 9/19/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 9/19/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 9/19/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 9/25/2025 | Approved Pending GreenApproval | ALIZAH MAYAGOITIA |
| Green Building Rough | 9/25/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Insulation | 10/9/2025 | Approved | RONNIE MEDINA |
| Shower Pan | 10/9/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 10/14/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 10/22/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 11/12/2025 | Approved | GEM DE OCAMPO |