4418 W 62ND ST 90043
Certificate Information: 4418 W 62ND ST 90043
- Application / Permit
- 24014-10000-00049
- Plan Check / Job No.
- B23LA24659
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Second-story addition to an existing 1 story detached ADU per GCS 65852.2 (e)(1)(B) AND LAMC 12.22A.33 (c),(d), AND (g)
- Permit Issued
- Issued on 3/15/2024
- Issuing Office
- Current Status
- CofO Issued on 12/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | NGHI SU |
| Corrections Issued | 1/13/2024 | NGHI SU |
| Quality Review Completed | 1/23/2024 | YOUNG KIM |
| Applicant returned to address corrections | 3/6/2024 | NGHI SU |
| Plan Check Approved | 3/15/2024 | NGHI SU |
| Issued | 3/15/2024 | APPLICANT |
| CofO in Progress | 12/9/2024 | SABAS ALONSO |
| Permit Finaled | 12/10/2024 | DEROLD HAUFF |
| CofO Issued | 12/10/2024 | DEROLD HAUFF |
| Permit Finaled | 12/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/19/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | ANTHONY TRAN |
| Sewer availability | Cleared | 1/24/2024 | ANTHONY TRAN |
| Construction near power lines | Cleared | 2/27/2024 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 3/15/2024 | NGHI SU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kang,, Danniel; Lic. No.: NA6242 | , |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 1176 N KNOLLWOOD CT ANAHEIM, CA 92801 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/18/2024 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 4/5/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 4/18/2024 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 4/18/2024 | Not Ready for Inspection | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2024 | Conditional Approval | JOSE MACIAS |
| Wood Frame | 4/24/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 5/9/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Conditional Approval | JOSE MACIAS |
| PLUMBING-Rough | 5/9/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 5/23/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 5/23/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 5/23/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 5/29/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 5/29/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 5/29/2024 | Approved | JOSE MACIAS |
| Wood Frame | 5/29/2024 | Not Ready for Inspection | JOSE MACIAS |
| Gas Test | 6/5/2024 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Approved | JOSE MACIAS |
| Insulation | 6/11/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/11/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 6/18/2024 | Approved | JOSE MACIAS |
| Gas Test | 7/2/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 7/16/2024 | Approved | JOSE MACIAS |
| Shower Pan | 7/16/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 8/15/2024 | Approved | JOSE MACIAS |
| Grounding or Bonding | 8/15/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Final | 8/15/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 8/15/2024 | Approved | JOSE MACIAS |
| Smoke Detectors | 8/15/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 11/14/2024 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 11/14/2024 | Approved | SABAS ALONSO |
| Green Building Final | 11/14/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/14/2024 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 11/14/2024 | Approved | SABAS ALONSO |
| Final | 12/6/2024 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 12/6/2024 | Approved | SABAS ALONSO |