205-207 S MEDIO DR 90049
Certificate Information: 205-207 S MEDIO DR 90049
- Application / Permit
- 24014-10000-00044
- Plan Check / Job No.
- B24LA00182
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan MAJOR REMODEL AND ADDITION TO (E) 1- STORY SINGLE FAMILY DWELLING TO BECOME 2-STORY SINGLE FAMILY DWELLING WITH 1-LEVEL OF BASEMENT AND ATTACHED TWO STORY ADU PER ORDINACE AND ATTACHED TWO CAR GARAGE NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 8/14/2024
- Issuing Office
- Current Status
- Issued on 8/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 1/12/2024 | JAD BASMA |
| Corrections Issued | 1/14/2024 | JAD BASMA |
| Quality Review Completed | 1/17/2024 | GARO TELMI |
| Applicant returned to address corrections | 2/16/2024 | JAD BASMA |
| Applicant returned to address corrections | 5/1/2024 | JAD BASMA |
| Plan Check Approved | 5/6/2024 | JAD BASMA |
| Issued | 8/14/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/20/2024 | LIAM ODONOVAN |
| Hydrant and Access approval | Cleared | 3/9/2024 | GILBERT URREA |
| Specific Plan | Cleared | 4/9/2024 | EDUARDO HERMOSO |
| Trees in Parkway | Cleared | 4/10/2024 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 4/12/2024 | TOMMY YIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2024 | LIAM ODONOVAN |
| Permit | Cleared | 4/17/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 4/17/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 4/17/2024 | LIAM ODONOVAN |
| Excavation more than 5-ft deep | Cleared | 4/25/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/6/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 5/6/2024 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/24/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| Footing/Foundation/Slab | 4/18/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 4/23/2025 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 5/20/2025 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 5/21/2025 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 6/17/2025 | Partial Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 6/24/2025 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 6/25/2025 | Partial Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 7/7/2025 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 7/9/2025 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/24/2025 | Partial Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 7/29/2025 | Conditional Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 7/30/2025 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 8/26/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 8/26/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/3/2025 | Partial Approval | HERBERT GIRON |
| Deputy Other (see comments) | 9/24/2025 | Approved | HERBERT GIRON |
| Structural Steel Frame | 9/24/2025 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Pre-Inspection | 2/4/2026 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Wood Construction | 6/11/2026 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2026 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 6/15/2026 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 6/22/2026 | Partial Approval | WILBER ROSALES |
| PLUMBING-Rough | 6/24/2026 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 6/24/2026 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 6/26/2026 | Partial Approval | HERBERT GIRON |