1735 N RAVENNA AVE 90744
Certificate Information: 1735 N RAVENNA AVE 90744
- Application / Permit
- 24014-10000-00040
- Plan Check / Job No.
- B24LA00137
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT PORTION OF (E) GARAGE TO 2-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 3/1/2024
- Issuing Office
- Current Status
- CofO Issued on 10/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | DANIEL YIP |
| Corrections Issued | 1/27/2024 | DANIEL YIP |
| Quality Review Completed | 1/30/2024 | PRANITA SHAH |
| Plan Check Approved | 3/1/2024 | DANIEL YIP |
| Issued | 3/1/2024 | APPLICANT |
| CofO in Progress | 10/4/2024 | EUGENE CASSIDY |
| Permit Finaled | 10/8/2024 | DEROLD HAUFF |
| CofO Issued | 10/8/2024 | DEROLD HAUFF |
| Permit Finaled | 10/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/12/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2024 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 2/13/2024 | KHAING AYE |
| Sewer availability | Cleared | 2/13/2024 | KHAING AYE |
| Clean Up Green Up | Cleared | 2/15/2024 | MAYELA VILLA |
| ZA Case | Cleared | 2/15/2024 | MAYELA VILLA |
| ZA Case | Cleared | 2/15/2024 | MAYELA VILLA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Jennifer Arianna; Lic. No.: C79156 | 3828 EARLE AVE ROSEMEAD, CA 91770 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/3/2024 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/9/2024 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 4/9/2024 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 4/9/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 4/9/2024 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/15/2024 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/19/2024 | Approved | EUGENE CASSIDY |
| Wood Frame | 6/12/2024 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 6/21/2024 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 6/27/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/15/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 7/15/2024 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 7/15/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/25/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/25/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/25/2024 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 7/25/2024 | Approved | EUGENE CASSIDY |
| Insulation | 7/30/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/7/2024 | Approved | EUGENE CASSIDY |
| Final | 9/27/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/27/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 9/27/2024 | Approved | EUGENE CASSIDY |
| Final | 10/1/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/1/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/3/2024 | Approved | EUGENE CASSIDY |
| Final | 10/3/2024 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 10/3/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/3/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 10/3/2024 | Approved | EUGENE CASSIDY |